I-70 Barrier & Median Improvements in Genesee, Morrison & Denver

Project Facts

  • Cost: $1.8 million
  • Contractor: Crus Construction Incorporated
  • Timeline: November 2018 - April 2019
  • Location: 3 sites on I-70:
    • Site 1: I-70 between the Lookout Mountain and Chief Hosa interchanges (mile points 252.7 to 255.3)
    • Site 2: I-70 between the Morrison Road and C-470 interchanges (mile points 258.5 to 259.8)
    • Site 3: West the of I-70/I-270 interchange, and the east side of Quebec Street overpass (mile points 4.4 to 5.1)

From November 2018 through April 2019, crews on this project will improve three sections of I-70 in Jefferson and Denver counties by replacing and installing median barrier, bringing the median safety measures up to current standards.

Work will be done at the following locations:

  1. Site 1: I-70 between the Lookout Mountain and Chief Hosa interchanges (mile points 252.7 to 255.3)
  2. Site 2: I-70 between the Morrison Road and C-470 interchanges (mile points 258.5 to 259.8)
  3. Site 3: West the of I-70/I-270 interchange, and the east side of Quebec Street overpass (mile points 4.4 to 5.1)

Schedule & Travel Impacts

  • Expect single-lane closures and shoulder closures.
  • Expect trucks and equipment entering and exiting the work zone.
  • Work is scheduled to run from November 2018 through April 2019.