I-25 Curb Ramps Castle Pines to Orchard

Project Facts

  • Cost: $1.2 Million
  • Contractor: Scott Contracting
  • Timeline: March - July 2021
  • Location:  On and off-ramps at 6 locations along I-25 in Arapahoe and Douglas Counties

Ridgegate Curb Ramps

Project Complete!

The Colorado Department of Transportation and prime contractor, IHC Scott Contracting, will begin installing new curb ramps (working from south to north) at the following six interchange locations: Castle Pines Pkwy, RidgeGate Pkwy, Lincoln Ave, County Line Rd., Dry Creek Rd. and Orchard Rd. Work will begin mid-April and go through July. The project is part of a larger statewide commitment by CDOT to provide greater accessibility to persons with disabilities.
Traffic Impacts


Work Schedule:

  • Monday through Friday, morning start times will vary
    based on type of work and location (not before 7 a.m.
    and no later than 9:00 a.m.). Weekdays, work will end
    by 5 p.m. in all locations.
  • Approximately 2 ramps per day will be removed and replaced. Work at each interchange will take approximately 2 weeks in the order below. All schedules are subject to change and weather dependent:
    • Castle Pines Pkwy.
    • Ridgegate Pkwy.
    • Lincoln Ave
    • County Line Rd
    • Dry Creek Rd
    • Orchard Rd

Traffic Impacts:

  • Construction zones are on the interchange streets (not I-25).

  • Minor traffic delays may be possible due to congestion. Nighttime work will require on-ramp closures at both RidgeGate Pkwy and County Line Rd., Saturdays only. A detour will be in place at these locations.

  • Please check www.cotrip.org for more details. Or, sign up for alerts at: http://subscription.cotrip.org.