I-70 over 32nd Ave Bridge Replacement

Weekly Traffic Impacts & Work Update


Traffic Impacts - Week of Oct. 22 to Oct. 28

 

Please be advised of the following lane closures, restrictions and planned work for next week for the I-70 over 32nd Avenue Bridge Replacement project in Jefferson County. Substantial project completion is expected by the week of Oct. 29.

*****

Sunday, Oct. 22 to Thursday, Oct. 26 - both directions of I-70 - overnight single & double lane closures 

  • Single lane closures will be taken nightly on both westbound and eastbound I-70 from 7 p.m. to 9 p.m., Sunday to Thursday
  • These single lanes will switch to double lane closures in both directions of I-70 at 9 p.m. and last until approx. 6 a.m. each morning
  • The double lane closures will alternate left to right, as needed
  • Late lane reopenings are possible and delays are expected
  • The project limits on I-70 extend from Mile Point 263 to MP 265
  • Single to double lane closures on westbound I-70 will also run concurrently during overnight hours Sunday to Thursday with the I-70 over Ward Road Bridge Replacement project which has limits from Exit 265 to Exit 266 (see Nearby Project Impacts below for specific details)
  • Motorists can expect longer than usual delays on westbound I-70 due to overnight lane closures in adjacent work zones
  • All schedules are weather and supply dependent and subject to change
Work includes guardrail patching, slope paving, removing barrier, concrete pours for curb and gutter and divider wall, installing cable rail, and seeding the median.
*****
Monday, Oct. 23 to Friday, Oct. 27 - 32nd Ave under I-70 - daily lane closures
  • Various lane closures will be in place from 7:30 a.m. to 4 p.m. daily in both directions of 32nd Ave under I-70 
  • Single lane closures may exist before 7:30 a.m. and after 4 p.m., Monday to Friday, as needed
  • Some Saturday work is expected
  • The south sidewalk on 32nd Ave is temporarily closed
  • Sidewalk access is limited to the north side of 32nd Ave
  • Caution is advised
  • All schedules are weather and supply dependent and subject to change
Wide view of new I-70 bridge structures over 32nd Ave in Wheat Ridge.
Aerial photography by John Klippel Photography.

Nearby Project Impacts


 I-70 over Ward Road Bridge Replacement
  • Single lane closures (7p.m. to 10 p.m.) switching to double lane closures (10 p.m. to 6 a.m.) will be taken on westbound I-70 within the project limits during overnight hours Sunday to Thursday
  • Westbound I-70 traffic will be shifted onto median detour pavement during overnight hours on Tuesday, Oct. 24, with a backup date of Oct. 26 in the event of inclement weather
  • The Ward Road on ramp to westbound I-70 will be closed overnight from 7 p.m. to 6 a.m. during the westbound I-70 traffic shift, with detour signage in place
  • The project limits on I-70 extend from MP 265 to MP 266.5
  • Intermittent daytime and overnight lane closures will be taken in both directions of Ward Road/CO 72 under the I-70 bridges Monday to Friday
  • The closures on Ward Road will exist from 7 a.m. to 6 p.m. Monday to Friday, and overnight from 7 p.m. to 6 a.m. as needed 
  • All construction schedules are weather and supply dependent and subject to change
Work includes moving barrier, restriping lanes, and realigning traffic.

Stay Connected!

 
Webpage: https://www.codot.gov/projects/i70-bridges-over-32nd-avenue
Hotline303.960.2825
Email:
i7032avebridges@comcast.net
Sign up for Text Alerts: text bridges to 8886650058
 
Road ConditionsCOtrip.org 
COtrip Planner App
bit.ly/COtripapp
Project Travel Alertsbit.ly/COnewsalerts
Lane Closuresbit.ly/laneclosures
decorative image
@ColoradoDOT on Facebook
@ColoradoDOT on Twitter
@ColoradoDOT on Instagram
@ColoradoDOT on YouTube
@ColoradoDOT on Flickr
Copyright © 2023 Colorado Department of Transportation All rights reserved.

Our mailing address is:

Colorado Department of Transportation
2829 W Howard Place
Denver CO 80204

You are receiving this email because you requested information regarding construction updates for the <Project Name>. Update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Colorado Department of Transportation · 2829 West Howard Place · Denver, CO 80204 · USA