Please be advised of the following lane closures and planned work for next week for the I-70 over 32nd Avenue Bridge Replacement project in Jefferson County.
*****
Sunday, Sept. 10 to Thursday, Sept. 14 - I-70 - overnight lane closures
- Double lane closures will be in place in both directions of I-70 within the project limits during overnight hours Sunday to Tuesday, with Wednesday and Thursday as a backup
- The double lane closures will be in place from approx. midnight (or earlier) to 6 a.m. on Sunday, Sept. 10 and from 10 p.m. to 6 a.m. Monday to Thursday
- Single lane closures in both directions of I-70 will also exist from 7 p.m. to 10 p.m. Monday to Thursday, as needed
- The project limits on I-70 extend from Mile Point 263 to MP 265
- All schedules are weather and supply dependent and subject to change
Work includes milling, paving, moving barrier, striping, and starting detour removal operations.
*****
Monday, Sept. 11 to Friday, Sept. 15 - 32nd Ave under I-70 - intermittent lane closures
- Intermittent single lane closures may exist during daytime hours in both directions of 32nd Ave under I-70
- The closures will be taken from approx. 8 a.m. to 5 p.m. Monday to Friday, as needed
- Overnight lane closures may also be taken in both directions of 32nd Ave from 8 p.m. to 5 a.m., as needed
- Single right lane closures may also exist on southbound Youngfield St through the work zone, as needed
- Sidewalk access is limited
- All schedules are weather and supply dependent and subject to change
|
|