Please be advised of the following lane closures and planned work for next week for the I-70 over 32nd Avenue Bridge Replacement project in Jefferson County.
*****
Sunday, Sept. 17 to Thursday, Sept. 21 - Westbound I-70 - overnight lane closures
- Single lane closures will be in place on westbound I-70 from 7 p.m. to 10 p.m. Sunday to Thursday
- Double lane closures will be in place on westbound I-70 within the project limits during overnight hours Sunday to Thursday
- Double lane closures will be taken from 10 p.m. to 6 a.m. Sunday, Monday, Tuesday and Thursday, as needed, and from 8 p.m. (still tentative) to 6 a.m. on Wednesday, Sept. 20
- The project limits extend from Mile Point 263 to MP 265
- All schedules are weather and supply dependent and subject to change
Work includes milling, SMA paving, and waterproofing the westbound I-70 bridge deck.
*****
Monday, Sept. 18 to Friday, Sept. 22 - 32nd Ave under I-70 - intermittent lane closures
- Intermittent single lane closures may exist during daytime hours in both directions of 32nd Ave under I-70
- The closures will be taken from approx. 8 a.m. to 5 p.m. Monday to Friday, as needed
- Overnight lane closures may also be taken in both directions of 32nd Ave from 8 p.m. to 5 a.m., as needed
- Single right lane closures may also exist on southbound Youngfield St through the work zone, as needed
- Sidewalk access is limited
- All schedules are weather and supply dependent and subject to change
|
|