I-70 over 32nd Ave Bridge Replacement

Weekly Traffic Impacts & Work Update


Traffic Impacts - Week of Sept. 24 to Sept. 30

 

Please be advised of the following travel advisory, lane closures, restrictions and planned work for next week for the I-70 over 32nd Avenue Bridge Replacement project in Jefferson County.

*****

Travel Advisory - Westbound I-70 Overnight Traffic Shift - Sept. 27-28


Westbound I-70 traffic within the project limits will be shifted into its final configuration during overnight hours on Sept. 27, with a backup date of Sept. 28. The following impacts will be in place:
  • Implementation of the traffic shift will include setting temporary barrier, restriping the lanes, and realigning traffic 
  • Motorists can expect a single lane closure followed by double lane closures and short delays on westbound I-70 during the overnight shift
  • The single lane closure will be taken from 7 p.m. to 10 p.m. followed by a double lane closure from 10 p.m. to 6 a.m.
  • The scheduled date of Sept. 27 is weather dependent, with a backup date of Sept. 28
  • Once the overnight shift is implemented, traffic will be in its final configuration
  • The project limits extend from Mile Point 263 to MP 265
  • Three lanes of traffic will be maintained in each direction of I-70 through the work zone
  • No impacts to eastbound I-70 or 32nd Ave. under I-70 are expected during the shift
Work includes moving barrier, restriping lanes and realigning traffic.
*****

Other Traffic Impacts - I-70 and 32nd Ave under I-70
 

Sunday, Sept. 24 to Tuesday, Sept. 26 - Westbound I-70 - periodic overnight lane closures 

  • Single lane closures may exist on westbound I-70 from 7 p.m. to 6 a.m. Sunday to Tuesday, as needed for equipment mobilization and preparation for the traffic shift
  • Single lane closures may switch to double lane closures from 10 p.m. and last until 6 a.m., Sunday to Tuesday, as needed
  • The project limits extend from Mile Point 263 to MP 265
  • All schedules are weather and supply dependent and subject to change
Work includes installing new guardrail, misc. conduit work, and preparing for the traffic shift.
*****
Monday, Sept. 25 to Friday, Sept. 29 - 32nd Ave under I-70 - daytime lane closures 
  • Various lane closures will be in place during daytime hours in both directions of 32nd Ave under I-70 
  • The closures will be taken from approx. 8 a.m. to 5 p.m. Monday to Friday
  • Some Saturday work is expected
  • Sidewalk access is limited and caution is advised
  • All schedules are weather and supply dependent and subject to change
Work includes asphalt and concrete work on the median.
*****
Drone views of replaced I-70 bridges over 32nd Ave showing westbound I-70 in the foreground prior to final traffic alignment and ground view of eastbound I-70 bridge structure. Aerial photography by John Klippel Photography.

Nearby Project Impacts


 I-70 over Ward Road Bridge Replacement
  • Periodic overnight single lane closures will be in place in both directions of I-70 within the project limits from 7 p.m. to 6 a.m. Monday to Thursday
  • The project limits on I-70 extend from Mile Point 265 to MP 266.5
  • Various daytime and some overnight lane closures will be taken in both directions of Ward Road/CO 72 under the I-70 bridges Monday to Friday
  • The daily closures on Ward Road will exist from 7 a.m. to 6 p.m. and overnight from 7 p.m. to 6 a.m.
  • All construction schedules are weather and supply dependent and subject to change
Work includes constructing detour pavement and forming and pouring sleeper and approach slabs.

Stay Connected!

 
Webpage: https://www.codot.gov/projects/i70-bridges-over-32nd-avenue
Hotline303.960.2825
Email:
i7032avebridges@comcast.net
Sign up for Text Alerts: text bridges to 8886650058
 
Road ConditionsCOtrip.org 
COtrip Planner App
bit.ly/COtripapp
Project Travel Alertsbit.ly/COnewsalerts
Lane Closuresbit.ly/laneclosures
decorative image
@ColoradoDOT on Facebook
@ColoradoDOT on Twitter
@ColoradoDOT on Instagram
@ColoradoDOT on YouTube
@ColoradoDOT on Flickr
Copyright © 2023 Colorado Department of Transportation All rights reserved.

Our mailing address is:

Colorado Department of Transportation
2829 W Howard Place
Denver CO 80204

You are receiving this email because you requested information regarding construction updates for the <Project Name>. Update your preferences or unsubscribe from this list.






This email was sent to <<Email Address>>
why did I get this?    unsubscribe from this list    update subscription preferences
Colorado Department of Transportation · 2829 West Howard Place · Denver, CO 80204 · USA