November 17, 2010 - Work Suspended to Make Way for Holiday Traffic - Northwestern Colorado/CDOT Region 3 - GRAND JUNCTION – Work on the I-70B Reconstruction Project will be suspended soon for the winter holiday season.
News Releases
June 24, 2011 - Northwestern Colorado/CDOT Region 3 - Project Completion Scheduled for Next Friday.
May 23, 2011 - PROJECT UPDATE - Northwestern Colorado/CDOT Region 3 - Chip seal resurfacing suspended until late June.
April 29, 2011 - Northwestern Colorado/CDOT Region 3 - Two sections to receive chip seal surface; some lane closures, motorists cautioned to drive slowly through work zone.
February 8, 2011 - Northwestern Colorado/CDOT Region 3 - Media Invitation: I-70 B Reconstruction Tour Feb. 9, 1:00 p.m.
February 3, 2011 - Northwestern Colorado/CDOT Region 3 - GRAND JUNCTION – Work on the I-70B Reconstruction Project will be restarting next Wednesday, February 9, 2011. Construction began on the project last July and work was suspended for the winter holiday shopping season on November 19, 2010.
August 19, 2012 - PROJECT UPDATE - Northwestern Colorado/CDOT Region 3 - 25 Road intersection to open by Thursday morning.
September 5, 2013 - Northwestern Colorado/CDOT Region 3 - Traffic to be moved back to original configuration next Wednesday morning.
April 3, 2013 - Northwestern Colorado/CDOT Region 3 - Project to increase safety, mobility - GRAND JUNCTION – The Colorado Department of Transportation will start Phase 3 of the I-70B (also known as US 6 & 50), reconstruction project next Monday, April 8.