Project Facts

  • Cost: $790,000

Project Team

  • Contractor(s): Asphalt Specialties Company

On April 24, 2017, crews started construction on US 287 at Larimer County Road (LCR) 17 between Loveland and Berthoud. Work will include repaving, minimal drainage improvements and paving on two bridges.

The project is intended to fix the bumps in the road on US 287. The work will also create a smoother driving experience across the highway's two area bridges. 


Schedule

Work is scheduled to last until June 26, with normal working hours running from 9 a.m. - 3 p.m., Monday through Friday. In special cases, these hours may include work from 9 p.m. - 6 a.m., Monday through Friday.

There will be lane-closures and lane shifts throughout the course of the project. The speed limit will be reduced to 50 mph.