US 550 Intersection Improvements at 17th, 22nd and 32nd Streets in Durango

Project Facts

  • Cost: $3.6 million
  • Contractor: Kirkland Construction
  • Timeline: Early October 2018 - Memorial Day 2019
  • Location: Where US Highway 550 (aka, North Main Avenue) intersects with 17th, 22nd and 32nd streets in Durango

Crews on this project completed the following work:

  • replaced signals;
  • improved the road;
  • constructed ramps and sidewalks at each intersection that comply with the Americans with Disabilities Act (ADA);
  • improved storm-drain inlets;
  • added and upgrading pavement markings for bike lanes, bike boxes and stop bars at crosswalks;
  • added a sidewalk at the small island (the triangle area at the east edge of Fassbinder Park) between 17th Street and West Park Avenue to provide pedestrians refuge at a lengthy crossing;
  • replaced a span-wire signal at 22nd Street with new signal heads, poles and mast arms;
  • replaced the traffic signal at 32nd Street; and
  • added and upgraded pavement markings between 32nd Street and East 2nd Avenue to provide two left-turn lanes onto southbound Main Avenue, one shared through/right turn-lane, and a small raised island at the intersection designating a free-flow right turn onto northbound Main Avenue (US 550).

17th Street

550 at 17th.jpg

22nd Street

550 at 22nd.jpg

32nd Street

550 at 32nd.jpg


Photos

Concrete at 17th 12-12-19.jpeg
Radar at 17th 12-12-19.jpeg
20181218_122753.jpg

20181211_105731.jpg
20181211_105644.jpg
20181211_105623.jpg

20181127_101402.jpg
20181127_101342.jpg
20181127_101333.jpg

20181220_120727.jpg
20181220_120727.jpg
0416191159a_Film1.jpg

0416191158_Film1.jpg