4th Street Bridge Construction in Pueblo

Project complete

Overview

On July 1, 2011, crews completed construction of the 4th Street Bridge in Pueblo.


Background Information

Feb. 20, 2008, Public Meeting Presentations:

  • Contractor Presentation
  • Designer Presentation

Construction of the 4th Street Bridge was officially awarded to Flatiron Constructors on Oct. 18, 2007, for a total cost of $36 million.

In 2009, Roads & Bridges Magazine selected the 4th Street Bridge for inclusion in its Top 10 Bridges of 2009. 


Bridge History

Bridge plans and a detailed description of existing conditions with site photographs can be found in the Structure Concept Report (FIGG, December 2001). Below are highlights of the information contained in that report as well as an updated description of conditions based on the latest CDOT inspection report dated March 18, 2002.

Existing Bridge Typical

The existing 4th St. Bridge, structure number K-18-Z, was constructed in 1958 and is approximately 1068 feet long and 68 feet wide. The bridge superstructure is constructed of built-up riveted steel plate girders with a cast-in-place mildly reinforced concrete deck (non-composite). Lead based paint was used for corrosion protection. The substructure bents are multiple column and bent cap construction. There are seven spans ranging in length from 117 feet to 202 feet. The maximum span length over the Arkansas River is 202 feet, over the UPRR, 182 feet and over the BSNF, 117 ft, 5 inches. The existing configuration results in five piers in the Pueblo Yard, and one pier on the western bank of the Arkansas River.

The existing bridge has a Sufficiency Rating of 24 out of a possible 100 (SIA, 2002). The sufficiency rating is a function of the structural adequacy, safety, serviceability, functional obsolescence, and public use of the bridge. The overall structural condition was rated as "meets the minimum tolerable limits to be left in place as is," and the bridge has been classified as "Structurally Deficient" (SD).

The latest inspection report indicates that there is inadequate load carrying capacity compared to the original and current standards of design. The bridge was originally designed for an HS20 vehicle load (36 tons), which was the standard at the time of construction. The State of Colorado now requires that new bridges be designed for an HS 24 or HL 93 vehicle load (45 tons), to reflect the heavier truck traffic common today. Inventory Operating level load rating, as reported in the latest inspection report, is summarized in Table 2.2 below. The table shows that the bridge deck and the girders in spans 3 through 5 have 65% and 75% of the capacity of the original HS 20 design loading at inventory level. This equates to 52% and 60% of current vehicle design load requirements.

Bridge and approach geometry are substandard by today's design requirements. The down grade of the bridge from west to east combined with tight curvature on the east end have been blamed for unsafe driving conditions especially in inclement weather. Similarly, the reverse curve on the west approach has been identified as undesirable and somewhat of a safety concern for motorists. The structure profile provides adequate vertical clearance to the Loop Ramp roadway and top of railroad tracks below.


Construction schedule

Project Milestone Dates Milestone Event
Project Award Oct. 18, 2007
Construction Start Date Dec. 12, 2007
Shift Traffic to New Structure (closing pedestrian access) March/April 2010
Complete Structure and Final Traffic Configuration (open to pedestrian traffic) April 2011
Project Complete June 2011

Project Description

Fourth Street is a major east west route through Pueblo connecting I-25, downtown, and western residential neighborhoods. The 4th St. Bridge carries State Highway 96A (SH 96A) across a small city street, the Union Pacific (UPRR) and Burlington Northern Santa Fe (BSNF) railroad yards (Pueblo Yard), a floodwall, and the Arkansas River. The Pueblo Yard is a major railroad system component with approximately 30 tracks at the bridge location, including one BSNF and two UPRR mainlines.

The existing 4th Street Bridge, structure number K-18-Z, has a Sufficiency Rating of 24 out of 100 and has become structurally deficient and functionally obsolete. Improvements will be made to enhance safety for motorists and pedestrians through new bridge construction and approach roadway modifications. Roadway alignment and profile improvements, structure replacement, drainage design, lighting, and urban design are part of the final overall strategy.

The bridge and roadway cross-section will be improved to accommodate current and future traffic demands on the 4th St. Corridor. The new cross-section includes two 12-foot travel lanes, a 6-foot inside shoulder, a 10-foot outside shoulder, and a 10-foot wide multi-use sidewalk in each direction.


Project Team

  • Colorado Department of Transportation
  • FHWA
  • Design Consultants
FIGG Project Management & Bridge Engineering
PBS&J Civil, Roadway, Traffic, Utilities, Environmental
Ayres Associates Hydraulics & Drainage
Goodson/MWWA Geotechnical, Geology
The Szynskie Group Lighting & Electrical Design
EDAW Urban Design & Landscape Architecture
Abel Engineering Survey & ROW Suppor
  • Stakeholders
    • City of Pueblo
    • Railroads (UPRR, BNSF)
    • Utility Companies
    • Business & Community Groups

Project Timeline

90% Plans Oct. 18, 2006
PS&E February 2007
Advertisement Spring/Summer 2007

Project Considerations

  • Railroad Coordination
  • City Coordination
  • Utilities
  • Phasing / Maintenance of Traffic
  • Arkansas River & Recreation Area
  • Access to Midtown Mall
  • Construction Access and Staging Areas
  • Environmental Compliance
  • Alternate Bridge Design (tentative)

Project Goals

  • Improve Safety for Motorists, Pedestrians, and Bicyclists
  • Improve Alignment and Profile
  • Increase Future Traffic Capacity
  • Provide Higher Functioning Level of Service
  • Provide RR Safety Clearances
  • Increase Load Carrying Capacity
  • Improve Drainage
  • Include Aesthetics and Urban Design
  • Community Involvement