CO 67 Overlay
About the Project
From June 2017 through July 2018, crews resurfaced, paved and completed other work on Colorado Highway (CO) 67 at two locations. Crews also installed guardrail, added signage and striped, and completed bridge work.
Project Facts
- Cost: $10.4 million
- Timeline: Early June 2017 - July 2018
- Contractor: Martin Marietta Materials
Project Updates
Week of Aug. 27, 2017
Site A
CO 67 ‐ Cripple Creek to Divide
Work this Week
- Daylight hours, Monday, Aug. 28 through Thursday, Aug. 31:
- Traffic reduced to one lane in both directions (measurements are approximate and may vary):
- See the map.
- Monday, Aug. 28: Southbound from mile point (MP) 63 to MP 62, and from MP 58 to MP 57
- Tuesday, Aug. 29: Southbound from MP 62 to MP 61, and from MP 57 to MP 55.5
- Wednesday, Aug. 30: Southbound from MP 61 to MP 60, and from MP 55.5 to MP 53
- Thursday, Aug. 31: Southbound from MP 60 to MP 59, and from MP 53 to 52.3
- Flaggers and pilot car present
- Speed-limit reductions in place
- 12-foot wide load restriction during construction
- Paving will begin about two weeks after this work.
- Traffic reduced to one lane in both directions (measurements are approximate and may vary):
- Friday, Sept. 1
- No work
Site B
CO 67 ‐ Woodland Park to Westcreek
Work this Week
(No work on Friday, Sept. 1, in observance of the Labor Day holiday weekend)
- Daylight hours, Monday, Aug. 28 through Thursday, Aug. 31
- Traffic reduced to one lane in both directions (measurements are approximate and may vary):
- See the map.
- Monday, Aug. 28: Northbound MP 80 to MP 82.5
- Tuesday, Aug. 29: Southbound MP 83 to MP 81.5, and northbound MP 91 to 92
- Wednesday, Aug. 30: Southbound MP 81.5 to MP 80
- Thursday, Aug. 31: Southbound MP 80 to MP 78.5
- Flaggers and pilot car present
- Speed limit reductions in place
- 12-foot-wide load restriction during construction hours
- Flaggers will stop bikers and pedestrians and direct them to follow roadway construction rules.
- Traffic reduced to one lane in both directions (measurements are approximate and may vary):
Construction schedules are subject to change based on weather/unforeseen circumstances or schedule changes.