From Monday, April 24, 2017, to Thursday, Oct. 19, 2017, crews made improvements to Colorado Highway (CO) 9 and US Highway 6, near I-70 in Dillon.
Project work included:
- Roadway repaving
- Installing ADA-compliant ramps
- Installing sidewalks
- Traffic loops
- Drainage improvements
Phased Work
Phase 1 Work:
- Removing and replacing curbs and gutters along CO 9
Phase 2 Work:
- Excavations, followed by drainage improvements and paving operations
Phase 3 Work:
- Milling and overlay operations, allowing the asphalt to line up with the new concrete improvements
Project Facts
- Cost: $11 million
- Annual Daily Traffic: 31,000
- Location:
- CO 9, mile points 101.6 to 107.0
- CO 6, mile points 208.7 to 210.7
Project Team
- Contractor(s): APC Southern Construction Company, LLC