CO 67 Bridge Replacement
Project Overview
This project will consist of a new bridge to replace the K-16-W timber bridge which was located on CO 67 in Fremont County, 5 miles north of Wetmore and 6 miles south of Florence. K-16-W was damaged beyond repair on July 31, 2012, and demolished in August. A two-lane temporary detour bridge adjacent to the original bridge site was constructed in August to keep CO 67 open until the replacement bridge is in place. Additional work will include drop structures and other improvements to stabilize the drainage channel, HMA pavement, bridge rail and guardrail.
Photos of the original structure and channel are available via a records request.
This project will be delivered using a modified design-build process. Project information, including the procurement schedule, will be provided on this webpage and updated as new information is received.
Project Schedule
The schedule shown below will be followed for this project leading to the award of the construction contract.
| Milestone | date |
|---|---|
| Issue Final RFP (Ad Date) | December 20, 2012 |
| AC/TA Meetings (2 Hour meetings, by appointment) |
January 2 and 3, 2013 |
| Final AC/TAs, and RFP Comments Due | January 10, 2013 |
| CDOT Response to ACs and TAs | January 17, 2013 |
| Contractors Bids Due | January 24, 2013 |
| Award Project | January 31, 2013 |
| Issue Notice to Proceed | February 2013 |
| Substantial Completion | July 19, 2013 |