CO 9 at Currant Creek
Project Overview
The project consists of replacing structure J-15-B on SH 9 in Fremont County; 11.3 miles north of the US 50 and CO 9 intersection. The existing structure intersects Currant Creek and is a triple span structure with steel girders, concrete deck, and concrete piers.
FASTER – Funding Advancements for Surface Transportation and Economic Recovery – is fully funding this project. Financed by vehicle registration fees, FASTER established a Statewide Bridge Enterprise, funding the maintenance and repair of Colorado’s most urgent structurally-deficient and functionally-obsolete bridges.
This section of CO 9 consists mainly of local traffic and is used for recreational activities such as camping, fishing, hunting, skiing and general access to the mountains. However, CO 9 is not considered a major access route to the mountains.
The intent of the project work is to replace the structure, while not changing the surface elevation of the floodplain. The 24-foot existing roadway width on the structure requires an on-site detour to be in-place for the replacement of the structure.
Project Update
The Colorado Department of Transportation (CDOT) was scheduled to begin initial preparations to replace the bridge on Monday, May 9, but due to the deck problem, started the project today. The lane where the hole is located is closed and a temporary signal currently is alternating one lane of traffic over the bridge. Sensors are monitoring traffic and activating the signal to keep the wait time for stopped vehicles to a maximum of five minutes.
A temporary detour has been constructed and is now in use. The demolition of the existing bridge is approximately 90% complete and will be 100% completed by Tuesday, June 1st. Construction on the new bridge substructure will begin on June 3rd.
The temporary detour is a one-lane alternating traffic configuration with a traffic signal alternating northbound and southbound traffic, 24 hours a day, seven days a week.
Vehicles wider than 12 feet are not permitted to travel through this area for the duration of the project due to the minimum lane width on the bridge and detour.
The project is scheduled for completion in September 2011.