Federal Boulevard Median Project 52nd Avenue to 67th Avenue

Project completed

Project Overview

In summer 2015, the Colorado Department of Transportation (CDOT) completed a $2 million safety improvement project on Federal Boulevard (US 287) between 52nd and 67th Avenues. The project included:

  • construction of median islands with street lighting and landscaped planters; pedestrian countdown signals at 67th Avenue
  • new traffic signal heads at 54th, 56th and 67th Avenues
  • new crosswalks at 64th Avenue
  • lighting under the Federal Boulevard bridge illuminating the Clear Creek Trail north of 60th Avenue

The project is intended to improve safety by consolidating left-turn movements to and from Federal Avenue. Special provisions have been made for emergency access. Project plans, which show access modifications, are available for download here. More information on the safety benefits of corridor access management strategies are available.

Project Background

Federal Boulevard has been the subject of multiple planning studies and outreach efforts. Of note, the Federal Boulevard Framework Plan (Plan) was adopted by the Adams County Planning Commission in September 2014. Page 20 of the Plan expands on past planning efforts and the reason for the median islands. The Plan involved an extensive public outreach process, which is described starting on page 50. Appendix K provides an illustration and summary descriptions of the long range vision for the Federal Boulevard corridor. 

Concurrently, the Tri-County Health Department and agency partners are finalizing the Federal Boulevard Health Safety Assessment, which will provide recommendations for better healthy outcomes, particularly in the areas of reducing obesity and and reducing traffic accidents. Median islands are one of the safety enhancements that will help improve the balance between vehicle, pedestrian and bicycle modes of travel.