In 1995, the City and County of Denver completed the Federal Boulevard Corridor Plan which identified potential roadway improvements for Federal Boulevard that would enhance the image and improve the safety and efficiency of the corridor for residents and visitors. As a follow-up to the Corridor Plan, this study has been initiated to:

  • Identify the primary transportation issues in the corridor, which based on preliminary analysis include:

      - Reduce higher than normal accident rates
      - Correct substandard lane widths
      - Improve deteriorated sidewalk conditions
      - Improve poor pavement conditions
      - Consider improvements to reduce traffic back-ups at bus stops
      - Improve parking conflicts with Federal Blvd.
      - Consider adding a center median
  • Develop and evaluate a series of alternatives that address these issues; and
  • Prepare an Environmental Assessment (EA) to determine the effects the alternatives would have on the corridor’s businesses, residents, and commuters.

On Monday, March 21, 2010 the Colorado Department of Transportation (CDOT) began a widening and reconstruction project on Federal Boulevard (Colorado Highway 88) between Alameda Avenue and 6th Avenue.

The project will reconstruct and widen approximately one mile of Federal Boulevard in concrete to accommodate an additional lane on northbound Federal Boulevard.  When complete, there will be three lanes in each direction with a raised median.  In addition, the traffic signals at the Federal Boulevard/1st Avenue and Federal Boulevard/2nd Avenue interchanges will be replaced and sidewalks will be widened to eight feet to improve safety for pedestrians.

Scott Contracting, Inc. is the contractor for this $7.8 million project scheduled to be complete by the end of January 2013.  The project is being funded by CDOT, the Federal Highway Administration and the City and County of Denver.

Project Purpose

The purpose of the Federal Boulevard project is threefold:

  • To improve the safety and efficiency of the roadway;
  • To accommodate the transportation needs of area residents and existing businesses; and
  • To provide multi-modal travel options and connections along Federal Boulevard between Alameda and 6th Avenues.

Improvements to Federal Boulevard are needed to correct existing and future safety concerns, existing and future congestion, existing roadway deficiencies, and to improve the connectivity of all transportation modes. Transportation needs typically fall into categories provided in technical guidance by the Federal Highway Administration (FHWA). For Federal Boulevard these categories are safety, capacity, roadway deficiencies and modal connectivity.

Safety

  • Accidents rates* involving property damage on Federal Boulevard are 9.54 accidents per million vehicle miles of travel compared to the statewide average of 2.61.
  • Accidents* rates involving injuries on Federal Boulevard are 3.29 accidents per million vehicle miles of travel compared to the statewide average of 0.97.
  • Accidents* rates involving fatalities on Federal Boulevard are 4.63 accidents per 100 million vehicle miles of travel compared to the statewide average of 1.29.
  • Northbound vehicular accidents are 30% higher than southbound vehicular accidents.

Capacity

  • By 2030, drivers at 3 of the 4 signalized intersections will experience delays of a minute or more.
  • By 2030, traffic volumes will exceed the roadway's capacity at 3 of the 4 signalized intersections.
  • By 2030, northbound traffic volumes will exceed the roadway's capacity at a higher level than southbound traffic volumes.

Roadway Deficiencies

  • The number and proximity of access points along Federal Boulevard increases the probability for accidents.
  • Highway industry guidelines caution the use of continuous two-way left turn lanes on roadways with five or more lanes.
  • Lane widths are substandard and inconsistent, varying from 9 feet to 11 feet.
  • Side streets are closely spaced and have off-set intersections.
  • Fixed objects (such as poles, curbs, signs) are located too close to the travel roadway.
  • Pedestrian and bicycle facilities such as sidewalks, identified pedestrian crossings, and Americans with Disabilities Act (ADA) ramps are insufficient.

Modal Connectivity

  • On-time performance for primary transit route is 78% compared to the industry standard of 90%, due in part to the existing congestion on Federal Boulevard .
  • The intersection of Federal Boulevard and Alameda Avenue is the third highest transfer location in the Regional Transportation District (RTD) system.
  • Route #30 Federal arrives every 10 minutes throughout the day.
  • Route #30 Federal has 59.4 boardings per hour, the 2 nd highest boarding rate of RTD's 35 mainline routes.
  • Every day, 1,200 people board buses on Federal Boulevard between Alameda and 6 th Avenues. Pedestrian infrastructure along the corridor, including to and from bus stops, is insufficient.

Blueprint Denver

The 2002 Blueprint Denver: An Integrated Land use and Transportation Plan identified the South Federal Blvd. Commercial Corridor as an Area of Change. Areas of Change are parts of the city where new growth or redevelopment can best be accomplished because of transportation choices and opportunities for mixed-use development. Channeling growth to older industrial areas, districts close to downtown, major arterial corridors, historical trolley corridors or existing and planned light rail stops will benefit the City as a whole.

The area south of Colfax Avenue received this designation because of its vibrancy as an ethnic corridor. The area is described as a high-traffic corridor that serves as a non-freeway, north-south route for the west side of Denver. However, due to the width of the travelway and the traffic volumes, the parcels fronting Federal Blvd. are not appropriate for pedestrian shopping uses. The plan recommends emphasizing corridor redevelopment that supports transit so that pedestrian and consumers are protected from the negative impacts of high traffic.

Study Area

The study area for the Federal Blvd. Environmental Assessment (EA) extends roughly 500 feet east and west of the centerline of Federal Blvd. and is bounded by West Alameda Avenue on the south, West Fifth Avenue on the north, South Hazel Court on the west, and South Decatur Street on the east.

Currently the Federal Blvd. corridor has the following characteristics:

  • Two northbound travel lanes
  • Three southbound travel lanes
  • Continuous center turn lane
  • Lane widths vary between 8 to 10 feet
  • Heavily-used transit corridor
  • Primarily retail establishments located along corridor
  • Surrounding neighborhoods are predominantly Hispanic and Asian

Study FAQ

Why is this study being done?

Federal Boulevard is a major highway corridor in the Denver region. From Alameda to 6th Avenue , Federal Boulevard is heavily used by pedestrians, cars and buses, with about 40,000 cars per day. Other stretches of Federal Boulevard have been improved throughout Denver . The City and County of Denver received federal funds to prepare a report, called an Environmental Assessment (EA).

What is an EA?

An EA is a comprehensive study that evaluates potential impacts - both positive and negative - of the various alternatives under consideration and is a requirement of the National Environmental Policy Act (NEPA) of 1969 for projects that will receive federal funding. The purpose of preparing an EA is to provide the community and decision makers with key information on alternatives under consideration with regard to their potential impacts to the built, natural, and social environments of the study area. If there are no significant impacts, a Finding of No Significant Impact (FONSI) is prepared. If the EA indicates there are significant impacts, an Environmental Impact Statement (EIS) must be prepared.

How long will the study take?

This study will take about two years. The EA is anticipated to be completed in late summer 2007 and the Finding of No Significant Impact (FONSI), if appropriate, is anticipated to be completed at the end of 2007.

How soon after the study is complete will construction start?

When the study is complete, it will take at least 18 months for the preparation of construction plans and acquisition of right of way.   Then construction can begin.

Team Collaboration

The Colorado Department of Transportation (CDOT), in association with the City and County of Denver , is conducting the Federal Blvd. Environmental Assessment. The Federal Highway Administration (FHWA) is the lead agency responsible for reviewing and approving the Environmental Assessment for this project.

Parsons Brinckerhoff is the consultant firm contracted to conduct and prepare the Environmental Assessment, technical studies and carry out the public involvement program.

Environmental Assessment

The EA is available for viewing at the following locations:

CDOT Region 6
Central Engineering
425 B Corporate Circle
Golden, CO 80401
(720) 497-6961

City and County of Denver
Clerk and Recorder Office
201 W. Colfax Avenue
Department 101
Denver , CO 80202
(720) 865-8400

Denver Public Library
Ross-Barnum
3570 W. First Avenue
Denver , CO 80219
(303) 935-1891

FHWA
Colorado Division Office
12300 West Dakota Avenue
Suite 180
Lakewood , CO 80228
(720) 963-3007

CDOT Region 6 Office
2000 South Holly Street
Denver , CO 80222
(303) 757-9372

There is a 30-day comment period for the EA, which is from November 19, 2007 through December 18th, 2007. All comments on the EA are due by December 18, 2007. They may be made through the website or by filling out the comment form and mailed or faxed to the following:

Judy Aranda
PB
555 17th Street, Suite 500
Denver , CO 80214
Fax : (303) 728-1936

The Proposed Action (Build Alternative) is Alternative 3 Curved. A detailed analysis of the impacts of this alternative can be found in the EA, which is posted above. The major features of this alternative are as follows:

  • Addition of a third northbound lane.
  • Widening of existing lanes to 11 feet.
  • Construction of a 16 foot raised median.
  • Widening of existing sidewalks/amenity zone to 8 feet.
  • Realignment and potential installation of a traffic signal at Bayaud Avenue .

The cross section for Alternative 3 Curved (the Build Alternative) can be seen below.  The view is from the center of the roadway, looking north.

Alternatives

Several preliminary alternatives were developed to address the needs of the corridor as described in the project overview. These alternatives were evaluated in the Environmental Assessment.

All but one of the alternatives were eliminated from further analysis during the different screening levels of the evaluation process. The cross-sections of all of the alternatives developed and a flowchart that shows the screening levels can be found below. The No Action Alternative and Alternative 3 Curved were evaluated in the Environmental Assessment. The No Action Alternative reflects making no changes to the existing conditions on Federal Boulevard, except for routine maintenance of the roadway. The No Action Alternative is used as a baseline for comparison to Alternative 3 Curved (Build Alternative) in the Environmental Assessment.

Project Update

Crews have completed the majority of paving operations on northbound Federal Boulevard between 5th Avenue and 2nd Avenue and temporary business access has been restored along this stretch. 3rd Avenue and Short Place remain closed for fire hydrant relocations, curb and gutter work and paving operations. This work is expected to take approximately two to three weeks to complete. In addition, conduit for new lighting will be taking place next week between 5th Avenue and 2nd Avenue and is expected to take seven to ten days. Following the conduit work, crews will work on sidewalks and driveways for approximately two to three weeks.

In addition, starting on Monday, January 30th, Xcel will begin installing a new gas main line and relocating services from 1st Avenue to Cedar. Two Xcel crews will be working on the gas line work and the work is scheduled to take 20 days to complete.

Federal Boulevard remains in a temporary alignment and motorists can continue to expect lane closures on Federal Boulevard from 8:30 a.m. to 3:30 p.m., Monday through Friday.

All work and schedules are weather permitting.

Project Schedule

The Federal Boulevard Environmental Assessment will take about two years to complete. The study started in August 2005 and is expected to be completed in early 2008. This is a tentative schedule of major milestones.  The schedule is subject to change:

March 2011- The project began with utility relocation and sanitary work.

April 2011- Reconstruction and widening of southbound Federal Boulevard began at 5th Avenue working north to south. This phase of the project is now complete.

November 2011- Reconstruction and widening of northbound Federal Boulevard begins at Alameda Avenue working south to north.

Spring 2012- Construction of the raised median begins.

January 2013- Construction completed.

Public Involvement

We are committed to working with you and the community to understand what issues you feel are important and learn what issues should be addressed in the Environmental Assessment study.

We plan to keep the community informed through public meetings, small group meetings, newsletters, and this website.

Public Meetings

The public hearing for the Federal Boulevard Environmental Assessment was held on December 4th, 2007 from 5:00 to 7:00 pm. Below are the display boards from the public hearing. 

Reminder that the comment period for the Environmental Assessment that began on November 19, 2007 ends on December 18th, 2007.

If you have any questions, please contact: Kara Swanson at 303-378-9237 or Ed Romero at 303-803-2941.

The Build Alternative that will be evaluated in the EA is Alternative 3 Curved.  The major features of this alternative are as follows:

  • Addition of a third northbound lane.
  • Widening of existing lanes to 11 feet.
  • Construction of a 16 foot median.
  • Widening of existing sidewalks/amenity zone to 8 feet.
  • Realignment and installation of a traffic signal at Bayaud Avenue.

The cross section for Alternative 3 Curved (the Build Alternative) can be seen below.  The view is from the center of the roadway, looking north.

Information Sheets

Federal Boulevard EA Project Information Sheet - October 2005 175kb

May 2006 Newsletter

Presentations

Public Scoping Meeting Presentation – October 2005 5MB - Revised May 2006

Public Involvement FAQ

How will public input influence the study?

Public input will help the project team and consultants understand how residents, business owners, and travelers in the corridor feel about existing transportation conditions, alternatives that should be evaluated, and issues to be addressed.

Are public meetings the only opportunity to comment?

Public input is not limited to public meetings. The project team will accept input in all forms including letters, comments submitted to through the Web site, and comment cards completed at presentations to civic, business and community groups. If you would like a presentation at a civic, business or community group, please contact Ed Romero, Public Information Coordinator (303) 860-9055.

How can I provide comments/feedback if I can't attend a public meeting?

See the contact information for the project team in the top right side of this website.

The Federal Boulevard Environmental Assessment will take about two years to complete. The study started in August 2005 and is expected to be completed in early 2008. This is a tentative schedule of major milestones.  The schedule is subject to change:

March 2011- The project began with utility relocation and sanitary work.

April 2011- Reconstruction and widening of southbound Federal Boulevard began at 5th Avenue working north to south. This phase of the project is now complete.

November 2011- Reconstruction and widening of northbound Federal Boulevard begins at Alameda Avenue working south to north.

Spring 2012- Construction of the raised median begins.

January 2013- Construction completed.

Federal Boulevard EA Project Information Sheet - October 2005 175kb

May 2006 Newsletter

Presentations

Public Scoping Meeting Presentation – October 2005 5MB - Revised May 2006

Public Involvement FAQ

How will public input influence the study?

Public input will help the project team and consultants understand how residents, business owners, and travelers in the corridor feel about existing transportation conditions, alternatives that should be evaluated, and issues to be addressed.

Are public meetings the only opportunity to comment?

Public input is not limited to public meetings. The project team will accept input in all forms including letters, comments submitted to through the Web site, and comment cards completed at presentations to civic, business and community groups. If you would like a presentation at a civic, business or community group, please contact Ed Romero, Public Information Coordinator (303) 860-9055.

How can I provide comments/feedback if I can't attend a public meeting?

See the contact information for the project team in the top right side of this website.