I-25, Denver to Colorado Springs Intelligent Transportation System Installation

Project complete

Project Overview

This project upgraded this stretch of highway with the following:

  • highway cameras
  • weather stations
  • fiber optic cable
  • traffic detection system
  • ethernet conversion of Intelligent Transportation System (ITS) networks

Work was completed in October 2016.

Benefits

There were critical gaps within the ITS system that impeded our ability to effectively manage incidents and traffic along both corridors. Adding cameras, weather stations, traffic detectors, and a robust and secure network will help us close gaps for effective incident management and traveler information in this corridor.

Project Team

  • Project Engineer(s): Scott Burger
  • Contractor(s): Paonia, Vaisala and Sturgeon