I-70 Centerline Tape
Project Facts
- Cost:
$430,000 - Average Annual Daily Traffic:
18,000-36,000
Project Team
- Contractor(s): Roadsafe Traffic Systems, Inc.
This project replaced worn and faded centerline skip lines on I-70 in both directions, from mile points 130 to 180.
Project work started on April 25, 2016, and was scheduled for completion on June 30, 2016. Working hours were 7 a.m. - 7 p.m., Monday through Friday.