I-70 Improvements from Deer Trail to Bethune

Project complete

Project Facts

  • Cost: $$623,007
  • Contractor: Dykhuis Drilling Corp. (doing business as Diamond Drilling & Sawing Co.)
  • Timeline: November 2018 to January 2019
  • Location: I-70 from Deer Trail to Bethune

About the Project

From November 2018 through January 2019, crews on this project will improve a nearly 100-mile stretch of I-70 in Arapahoe, Elbert, Lincoln, and Kit Carson counties.

Work on this project includes:

  • sealing cracks within the concrete pavement in both directions of the highway.

Travel Impacts

  • lane closures and shoulder closures
  • a speed limit reduction and delays

This project is weather-dependent, and this schedule may change.