I-70 Frisco

Project complete

Project Facts
 

  • Cost:
    $6.5million
  • Average Annual Daily Traffic:
    27,000

Project Team

  • Contractor(s): TBD/li>

Project Overview

Crews on the I-70 Frisco project will repair 6.5 miles of road to remove rutting from truck chains.

Work will include laying hot mix asphalt on the eastbound right lane and ramps.

Work is scheduled for September - October 2016, with work scheduled for daytime hours, Monday through Friday.