I-70 Improvements Between Avon & Vail

Project complete

Project Facts

  • Cost: $10.1 million
  • Contractor: United Companies
  • Timeline: April - October 2019
  • Location: I-70 between Avon and Vail (mile points 166-174.5)

About the Project

Crews on this nearly six-month-long project have resurfaced more than eight miles of I-70 between Avon and Vail in Eagle County.

Other work included:

  • upgrading guardrail
  • repairing bridge joints and bridge rail
  • completing erosion control