I-70 Bridge from Stanley Road to Fall River Road in Clear Creek County
Project Overview
CDOT and contractor SEMA Construction have completed construction of the two-lane vehicle bridge connecting Stanley Road to the I-70/Fall River Road interchange at Exit 238. The bridge is open and Stanley Road has been restored to its original two-lane configuration.
This project was designed to improve driver, bicycle and pedestrian accessibility between I-70 and Stanley Road which is a popular gateway to year-round recreational and tourist destinations.
Construction began in May 2019 and the bridge features a 10-foot wide sidewalk with pedestrian guardrails, signs and lighting to improve safety. Crews raised an approximately 845-foot long stretch of Stanley Road by about four feet to match the elevation of the new bridge and added guardrails along Stanley Road at the approaches to the bridge. The eastbound I-70 on- and off-ramps at Exit 238 were also repaved.
Crews will return in spring 2020 when the weather warms up to paint the railings, add landscaping to the median at the interchange and make other aesthetic improvements.
Project Facts
- Cost: $2.5 million
- Contractor: SEMA Construction
- Timeline: May 2019 to August 2020
- Location: west of Idaho Springs at I-70 Exit 238, between Stanley Road and Fall River Road
Frequently Asked Questions
Will the new bridge be high enough for rafters and kayakers to safely navigate the creek underneath?
Yes. The rafting companies were involved in the design process so the bridge's design will not impact any rafters or kayakers. This is the main reason CDOT is raising Stanley Road by about four feet.
Yes—Clear Creek will be open as usual and the construction should not impact any rafting activities this season. CDOT held a public meeting on April 18, 2019, to discuss this issue. Girder erection will take place at night to avoid any disruption to recreational activities.
Yes; there will be a single-lane closure on westbound Stanley Road in the construction zone. Temporary traffic signals will safely direct two-way travel onto one lane.
CDOT will implement a shorter wait time (90 seconds or fewer) for live traffic queues on eastbound Stanley Road (rafter buses included).
No; there are no proposed bicycle or pedestrian restrictions on Stanley Road or Fall River Road for the duration of the project. However, caution is advised due to the single-lane configuration and presence of construction equipment and personnel in the work zone.