I-76 at US 85 Reconstruction

Project complete

Project Overview

From October 2016 to December 2017, crews reconstructed Interstate 76 at US Highway 85. The most noticeable changes are along westbound I-76, where the project improved the curve approaching the southbound US 85 merge area, and added a lane from southbound US 85 to 96th Avenue.

Before the project, westbound I-76 had a high accident history, including several truck rollover incidents. The superelevation of the curve, which is the raised or "banked" section, was redesigned to current standards. Traffic operations have also improved at the southbound US 85 on-ramp. There are now two lanes entering I-76 instead of one.

For a year, both directions of I-76 were down a lane in each direction while crews completely reconstructed the highway from 96th Avenue through the US 85 interchange. Major project features included improving the westbound I-76 curve at US 85, constructing a new auxiliary lane from southbound US 85 to 96th Avenue and full replacement of deteriorated concrete pavement. The project also improved roadway drainage, lighting and water quality measures.

Project Facts

Project Team

  • Contractor(s): Villalobos Concrete Inc.

Traffic Impacts

  • An 11-foot width restriction is in place on I-76 near US 85
  • Truckers:
    • Only one lane is available on westbound I-76, between mile points 11.7 and 12.7, until October 2017
    • A width restriction of 11 feet is in place
    • Travel width is physically restricted by concrete barrier walls
    • If you have a wide load, use an alternate route
    • There are no exits or places to turn around within the work zone.
    • Westbound over-width vehicles must exit by CO 2 (Sable Boulevard), Exit 16
    • The width restriction also applies to eastbound I-76
    • Eastbound over-width vehicles must exit by 96th Ave., Exit 11