I-25 Interchange Curb Ramps in Denver County
Project completed
            
          About the Project
Seventeen locations have/will see curb ramp improvements within this project scope:
- Belleview (completed),
 - Hampden (completed),
 - Yale (completed),
 - Evans (completed),
 - University (completed),
 - Downing (completed),
 - Emerson (completed),
 - Ogden (completed),
 - Washington (completed),
 - Clarkson (completed),
 - Cedar Ave (completed),
 - 8th Ave (completed),
 - 16th St. (completed),
 - 20th St. (completed),
 - Park Ave West, (completed)
 - 38th Ave (completed) and Fox.
 
Work is expected to go through mid-March of 2022 and is part of a larger commitment by CDOT to provide better accessible to multi-modal travelers.
Information and maps will be provided separately for each area of work. To get the most current information, please check cotrip.org for more details.
Work Schedule
- Each location will take approximately two weeks.
 
Traffic Impacts
- Monday through Friday work hours will be from 8:30 a.m. to 3:30 p.m. Construction zones are on the interchange streets only (not I-25).
 - Travelers can expect alternating lane closures, and turn lane closures. Some nightwork and full closures are anticipated.
 - Information and maps will be provided separately for each area of work.
 - To get the most current information, please check cotrip.org for more details. Or, sign up for alerts at: subscription.cotrip.org
.  
Project Facts
- Cost: $1.6 Million
 - Contractor: IHC Scott
 - Timeline: August 2021 to February 2022
 - Location: 17 Locations on I-25 in Denver County
 