I-25 & 104th Avenue Interchange
Project completed
Project Overview
On July 6, 2009, the Colorado Department of Transportation (CDOT), in partnership with the City of Northglenn, will begin a bridge replacement project at I-25 and 104th Avenue. The project will replace the existing 104th Avenue bridge over I-25, which was originally constructed in 1962 and is one of Colorado's structurally deficient bridges. When complete, the new bridge will accommodate an additional left turn lane from eastbound 104th Avenue to northbound I-25. Hamon Contractors, Inc. the is contractor for this $6.5 million project scheduled to be complete by the end of September 2010.
Project Schedule
This is a tentative schedule:
- Phase 1- Remove the median on 104th Avenue to Bannock Street and patched it. This phase was completed in July.
- Phase 2- Mid-July through mid-November: The northern portion of the bridge will be demolished and rebuilt. This phase is underway.
- Phase 3- Mid-November through mid-March 2010: The center portion of the bridge will be demolished and rebuilt.
- Phase 4- Mid-March 2010 through to mid-September 2010: The southern portion of the bridge will be demolished and rebuilt. This will complete the project.