I-25 Widening (Lane Balance) from Lincoln Avenue to County Line Road

Project Completed

Project Overview

This project added an additional lane in each direction on I-25 from Lincoln Avenue to County Line Road, resulting in four lanes in each direction south of the C-470 interchange. In addition to expanding capacity on I-25, crews replaced asphalt with concrete to better match the I-25 corridor. This project improved the traffic patterns from and to all affected ramps as well as constructed new pedestrian connections. Interstate Highway Construction (IHC) was selected as the contractor for this high priority project.

During construction, three lanes of traffic were maintained in each direction with limited exceptions for night work, fast-track concrete work and major traffic shifts. Four lanes opened along northbound I-25 in November 2015. The fourth lane of southbound I-25 opened in early March 2016.


Project Archives

Check out these resources for background on this project:

Videos

 


Construction Phasing

The project will be completed in six general phases.

  • In October 2014, the Project reached the first significant milestone – completion of Phase 1. During Phase 1, the median barrier was demolished and temporary pavement was placed in order to shift all traffic to the west side of the highway. 
  • Phase 2 was substantially complete in June 2015. Phase 2 included constructing three northbound I-25 lanes and the outside shoulder, ramp reconstruction, building a new multi-use trail on the east side of I-25 and installing water quality ponds.
  • Phase 3 occurred in June and July 2015. The project team identified significant advantages associated with completing the project under a modified construction phasing plan. Part of that plan required a temporary traffic split of northbound I-25 while permanent concrete was placed within the work zone in the center of northbound I-25.
  • Phase 4 shifted all northbound I-25 traffic onto the newly constructed concrete to create a work zone between northbound and southbound I-25. Crews installed permanent concrete in the center section of I-25 in July and August 2015.
  • Phase 5 began in September 2015 with a southbound I-25 traffic shift onto new pavement placed during Phase 4. This phase constructed the southbound lanes along with shoulder and ramp improvements.
  • Phase 6, the final project phase, installed permanent median barrier and lighting. Traffic was moved into final lane configuration in March 2016. 

The project was substantially complete by March 2016.


Funding

Project Partnering Amount
FASTER $15,850,000
HOT $400,000
DRCOG $10,150,000
Douglas County $5,500,000
City of Lone Tree $250,000
Park Meadows Metro District $180,000

Total Cost

$32.33 Million