I-25 North Design Build (Colorado Springs)

Project complete

Overview

The purpose of the I-25 North Design Build project is to improve safety and increase capacity, by providing a minimum of six through lanes for Interstate 25 at the north end of Colorado Springs between the Woodmen Road Interchange (Exit 149) and the Monument Interchange (Exit 161). CDOT’s ultimate goal is to provide eight lanes (four lanes in each direction) through Colorado Springs, to north of the Briargate Parkway Interchange (Exit 151), and six lanes north to the Monument Interchange (Exit 160), consistent with the I-25 Environmental Assessment (EA).

A majority of the CDOT I-25 North Design Build project is on an easement from the United States Air Force Academy (USAFA).  The USAFA was a cooperating agency in the development of the I-25 EA.  The I-25 EA mentions the USAFA concerns and commitments that need to be followed for any improvements to I-25 on USAFA property.  The concerns are briefly mentioned below and more detailed information can be found in the I-25 EA regarding commitments to these listed concerns:

  • Security Concerns
  • Visual Impacts
  • Airspace Issues
  • Historic Issues
  • Threatened and Endangered Species
  • Wildlife and Vegetation
  • Safety Concerns
  • Ackerman Overlook
  • Multi-Use Trails
  • Noise
  • Water Resources
  • Construction Impacts

The budget for this project is anticipated to be $60-66 million, and the intent of CDOT is to maximize the following project goals:

  1. Alleviate corridor congestion with expansion and augmentation of other transportation elements
  2. Minimize the effects of the project to the surrounding natural environment.
  3. Reduce project impacts on travelers
  4. Complete the Project by November 16, 2014

Project Schedule

Tentative Schedule (All Dates are Subject to Change)

Issue Letter of Interest

April 12 – May 3, 2012

Value Engineering Study

January 16-20, 2012

Project Briefings

Ongoing

Letter of Interests Due

May 10, 2012

Issue Request for Qualifications (RFQ)

May 17, 2012

Deadline for Submitting RFQ Questions

May 31, 2012

CDOT Response to RFQ Questions

June 13, 2012

Final RFQ Addendum Issued

June 20, 2012

I-25 Re-Evaluation Complete

Late April – Early May, 2012

Statement of Qualifications (SOQ) Due

July 11, 2012

Evaluation of SOQ's Complete/Short List

July 12-20, 2012

Notify Short Listed Submitters

July 25, 2012

Issue Draft RFP to Short List

July 30, 2012

Industry Review of Draft RFP

August 20-24, 2012

CDOT Modifies Draft RFP

August 27-31, 2012

CDOT Issues FINAL RFP

September 5, 2012

TA & AC Meetings

October 1-5, 2012

Submitters TA’s & AC’s Due

October 12, 2012

CDOT Response to TA’s & AC’s

October 19, 2012

PMJM BA/BO

October 1, 2012

Final Proposals are Due

November 16, 2012

Evaluate Proposals and Awards Contract

November 19-27, 2012

Notice to Proceed

December 18, 2012

Substantial Completion Date

December 31, 2014