North I-25 Express Lanes: US 36 to 120th Avenue

Project completed

About the Project

In October 2013, the Colorado Department of Transportation (CDOT) began a safety and mobility project on a six-mile segment of I-25 between US 36 and 120th Avenue.


Project Benefits

  • Maximizes the use of the existing highway infrastructure to expand the capacity of I-25 by adding one HOV/tolled Express Lane in each direction
  • Resurfaced the existing general purpose lanes along this six-mile stretch
  • Connect directly with the existing I-25 Express Lanes, leading into and out of downtown Denver
  • Provides motorists the option of carpooling or paying a toll for a faster, more reliable commute, or using the existing general purpose lanes for free

Project Schedule

This project is now complete. Construction on the project began in October 2013. The contractor will provide regular construction updates on the progress of the work.  All construction is expected to be complete in January 2016.

Read information about the current project to extend North I-25 Express Lanes from 120th to the Northwest Parkway/E-470.


About the Express Lanes

In spring 2016, the High Performance Transportation Enterprise (HPTE) and CDOT opened both the northbound and southbound I-25 Express Lanes between US 36 and 120th Avenue. The lanes extend the existing Central 1-25 Express Lanes in Denver, which end at US 36.

Testing was completed and tolling began in spring 2016. Drivers can choose to ride a bus, pay a toll as a single driver, or carpool for free with an ExpressToll account and Switchable HOV Transponder. The three adjacent general purpose lanes continue to be free.

Sound Walls

New sound walls have been installed along northbound I-25 between US 36 and 84th Avenue, and adjacent to the bike path between 104th and 120th avenues. New sound walls have also been constructed along southbound I-25 between 120th Avenue and Thornton Parkway.


Project History

On June 22, the U.S. Department of Transportation awarded the Colorado Department of Transportation (CDOT) a $15 million federal grant to complete the funding package and $44 million investment to build the I-25 North Express Lanes Project, between US 36 and 120th Avenue, allowing for one new managed toll lane in each direction on the highly congested six-mile stretch of Interstate 25 (I-25). The Regional Transportation District’s (RTD) Express Buses will also have access to the new managed lanes, increasing reliability and providing for system expansion.

The I-25 North Express Lanes offer a high-value, low-cost investment that would ensure sustainable congestion relief in the northern Denver metropolitan area.  The northern segment of I-25 is one of the most congested corridors in the metropolitan area with traffic jams spanning nearly four hours during morning and evening peak periods with traffic operating at 15 miles per hour verses the posted 55-65 miles per hour speed limit.

A Record of Decision (ROD) for the North I-25 Final Environmental Impact Statement (FEIS) signed in December 2011, identified the need for extending the managed lanes on I-25 north of US 36 into Adams County. The extension will provide meaningful relief and a congestion-free alternative for travelers when choosing to carpool, utilize transit, or pay a toll to access the express lanes.

The I-25 North Express Lanes expand the regional network of transit by providing a direct link from Denver’s northern metropolitan region to the region’s primary multimodal hub at Denver Union Station. These lanes also connect to a coordinated system of managed lanes; connecting to the existing I-25 Express Lanes to the south and the soon-to-be-completed US 36 Express Lanes and Bus Rapid Transit Project between Denver and Boulder to the west.