I-70 & CO 58 Interchange

Project complete

Project Overview

On February 7, 2007, the Colorado Department of Transportation (CDOT) began an interchange improvement project at I-70 and Colorado Highway 58 in order to improve access. The $23 million project will construct two new ramps and reconstruct or realign three other ramps:

  • A new ramp from eastbound I-70 to westbound CO 58 will be constructed
  • A new ramp from eastbound CO 58 to westbound I-70 will be constructed
  • The existing ramp from eastbound CO 58 to eastbound I-70 will be realigned and reconstructed without replacing the existing bridge
  • The existing ramp from westbound I-70 to westbound CO 58 will be realigned and reconstructed
  • The existing ramp from Youngfield Street to eastbound I-70 will be relocated approximately 1/4 mile to the south to accommodate a longer acceleration lane.

The project also constructs the 40th Avenue underpass, which will add access for the Cabela's development in the future. The underpass will cost approximately $7.2 million and is funded by the City of Wheat Ridge.

Project Facts

Cost: $23 million
Contractor: Ames Construction, Inc.
Start Date: February 7, 2007
End Date: March 2009

Project Schedule

Below is a tentative schedule of major construction activities. This does not list all closures or activities and the schedule can change depending on weather.

2008

  • June 2008 - The ramp from eastbound CO 58 to westbound I-70 is open. The ramp from eastbound CO 58 to eastbound I-70 has been realigned and reconstructed. The ramp from Youngfield Street to eastbound I-70 has been realigned and reconstructed. The 40th Avenue underpass is approximately 80% complete and work is underway on the new ramp from eastbound I-70 to westbound CO 58.

2007

  • February 2007- The project begins with preparatory work, including irrigation work and signing. Traffic will not be impacted until the end of the month when crews begin median widening on I-70 and temporary alignments are required.
  • March 2007- Construction of the ramp from eastbound CO 58 to westbound I-70 begins. Traffic will be reduced from four 12-foot lanes to three 11-foot lanes and the bike path under the bridge will close during various construction activities. Work on this ramp will be completed in June 2007. Demolition is scheduled for March 7 to 13 and girder installation is scheduled for April 7. Both activities will require the bike path under the bridge to be closed.
  • April 2007 – Drainage work on Youngfield Street begins and will continue through mid-June. Lane closures are expected.
  • May 2007 - Construction of the new ramp from eastbound I-70 to westbound CO 58 begins. Lane closures will be required at times. Construction of the new ramp will be complete in October 2008. The first girders will be installed in September 2007 with the first deck pour scheduled for February 2008.
  • June 2007 - Reconstruction begins on the ramp from Youngfield Street to eastbound I-70. Lane closures will be required on both Youngfield Street and I-70 through July 2007. Reconstruction also begins on the ramp from eastbound CO 58 to eastbound I-70. Lane closures can be expected on CO 58 and I-70 through March 2009.
  • November 2007 - Reconstruction begins on the ramp from westbound I-70 to westbound CO 58. Lane closures can be expected on I-70 and CO 58 through May 2008.