I-70 Exit 31 Horizon Drive Roundabouts
Project Facts
- Cost:
$5.25 million (RAMP) - Average Annual Daily Traffic:
18,000 (on I-70
Project Team
- Contractor(s): M.A. Concrete Construction
Project Overview
The I-70 Exit 31 Horizon Drive Roundabouts project was a 12-month construction project on Horizon Drive at the interchange with Interstate I-70 (Exit 31) in Grand Junction.
The project included:
- the construction on Horizon Drive of two modern-style roundabouts that will help improve traffic flow and safety;
- adding environmental aesthetics to the area;
- ramp upgrades;
- concrete sidewalks and gutters;
- re-surfacing; and
- a new access route for the Grand Junction Visitors Center along Visitor’s Way .
Roundabout-Driving Tips
- When entering the roundabout, yield to traffic already navigating it.
- When a safe gap is available, merge into roundabout traffic.
- As you travel the roundabout, pay attention to signage and merging vehicles.
- In the roundabout, you are allowed the right-of-way, but pay attention to inexperienced roundabout travelers.
- When you reach your desired exit point, signal to alert fellow motorists that you are exiting the roundabout and safely move out of it.
Reminders
- Exits should always be smooth; if you're making a sharp turn (greater than 90 degrees) when exiting, check your traffic directions!
- Pay attention to pedestrians navigating the roundabout, and make note of painted crosswalks and signage.
- Please be patient and respectful of other drivers. While roundabouts are designed to improve traffic and pedestrian safety, many motorists are unfamiliar with their unique requirements.
Traffic roundabouts will improve the intersection by maximizing traffic flow, alleviating congestion, and increasing safety for both motorists and pedestrians. With the creation of the roundabouts, the existing traffic signals were removed. The Horizon Drive Business Improvement District commissioned the creation and installation of six horse sculptures to the completed product to give the area a cohesive look and feel.
This project combined the collaborative efforts of CDOT, the City of Grand Junction, the Horizon Drive Business Improvement District and the Ute Water Conservancy District. M.A. Concrete Construction of Grand Junction was the prime contractor for the project.
CDOT provided the major funding for this $6.6 million project, while the City of Grand Junction, the Horizon Drive Business Improvement District and Ute Water Conservancy District have provided additional funding.
Project Updates
Completed construction
- water line work, except for abandoning of one service line on Visitors Way
- storm sewer, except for completion of inlets G1 and G3, due to traffic detours, and the added inlet on line EE by the Shell Station
- Vistors Way
- Horizon 70 Court
- all Portland Cement Concrete Paving, as of June 2, with the ability to support traffic by Thursday, June 9
(The last two pieces were the bottom of the eastbound off-ramp, and a piece of the outer lane on the south roundabout near the eastbound off-ramp.) - westbound off-ramp and westbound off-slip-ramp, except for final overlay
- Double Tree parking Lot, except for landscaping in islands
- Horse sculpture foundations (caissons) sculpted (to be installed in roundabouts in mid-July)
- Electrical boxes and receptacles in roundabouts
Underway/Ongoing
- westbound on-ramp curb and gutter work, including hot mix asphalt paving
- eastbound off-ramp curb and gutter work, and paving
- eastbound on-ramp paving on the north side and final overlay
- Horizon Drive median islands (currently underway) and hot mix asphalt overlay
- south and northbound roundabout sculpture lighting, landscaping, irrigation, truck apron (about one-third remaining) and median edging
- Super 8 parking lot curb and paving
- Taco Bell parking lot curb and gutter, and paving
- street lighting (underway with most bases in, with poles and lights raised within next few weeks)
- pedestrian lights within the next month or two (Light bases are installed.)
- project-wide landscaping (completed near Zarlingos and Taco Bell, and on eastbound on-ramp)
- project-wide irrigation
- final signing and striping (dependent on sealing of concrete paving and asphalt overlay)