I-70 Reconstruction Seibert to Stratton
Project Overview
In July 2016, CDOT completed work on a four-mile stretch of Interstate 70 between Seibert and Stratton. The project included concrete overlay as well as shoulder and guardrail improvements in both directions of I-70, between mile points (MPs) 410.9 and 406.9.
Project Facts
- Cost:
$30.8 million
Project Team
- Contractor(s): Castle Rock Construction Company of Colorado
This work came as an extension of highway repairs, which took place between MPs 410.8 and 418.3 from March to November 2015.
The contractor on this $19.8 million project is Castle Rock Construction Company of Centennial, Colorado. The project is scheduled for completion in late November 2015.
Project Benefits
This project will improve safety, the condition of the highway surface, and extends its life by up to 30 years. Much of the work of this project consisted of removing old deteriorated pavement and overlays and replacing this surface with longer-lasting concrete. This concrete will provide an increased longevity to the roadway surface and decrease the frequency of reparative overlays required on damaged parts of the highway.
Other work included repair work on four bridges, as well as shoulder upgrades, and guardrail removal and improvement, intended to provide greater safety to travelers on the interstate.
Significant project milestones:
- 510,000 square yards of concrete/asphalt was removed and recycled/reused as either road base or concrete aggregate
- One-hundred percent of the projects dirt work is complete. An estimated 35,000 cubic yards of embankment has been placed
- Ten miles of shoulder, along with guardrails in each direction, were upgraded to improve safety for motorists through the corridor
Project Background
On March 25, 2015, the Colorado Department of Transportation (CDOT) began a reconstruction project on Interstate 70 between Seibert and Stratton. Work includes a concrete overlay of 7.5 miles of pavement and repair of four bridges, as well as upgrades to shoulders and guardrail along the highway from Mile Marker 410.8 to Mile Marker 418.3. Both directions of I-70 will be reduced to one lane in each direction in a head-to-head configuration. During the concrete paving operation the Vona interchange will be closed and US 24 will be used by local traffic. The work also includes shoulder improvements, slope flattening to improve sight distance and sections of new guardrail.
Project Progress
The project remained on schedule, despite the area receiving a total of 10 inches of rainfall in May. The following are some significant milestones of the project:
- Overall, the project is 40 percent complete, and work has included concrete paving, asphalt paving, dirt work and bridge repairs
- Over 50 percent of the project’s dirt work is complete. An estimated 30,000 cubic yards of embankment has been placed
- Concrete paving of the eastbound lanes is 70 percent complete
Travel Impacts
Beginning Friday, July 31 and continuing through October, CDOT will switch all traffic onto the newly completed concrete eastbound lanes of I-70 from Seibert to Stratton. The traffic will be in a head-to-head configuration in the new eastbound lanes, as crews reconstruct the westbound lanes as part of a larger interstate reconstruction project that improves the existing infrastructure of both directions of I-70 from Seibert to Stratton.
Crews will work Monday through Saturday during daylight hours, with some Sunday work anticipated. Speed limits will be reduced to 55 mph through the work zone for both the safety of the traveling public as well as construction crews working along the highway.