I-70 Vail Underpass
Project Overview
- Created an I-70 underpass near I-70 mile point 175, connecting the north and south frontage roads between the Vail Town Center and West Vail interchanges.
- Will help relieve congestion at the interchanges and prevent vehicles from queuing at the I-70 exits at Vail Town Center and West Vail.
- Will help reduce repetitive I-70 local traffic by providing a direct connection between the core resort village areas and the West Vail mall area.
- Will enhance multi-modal transportation opportunities within the Town of Vail.
As of Oct. 13, 2017, the new Sandstone Underpass is open to vehicle, bicycle and pedestrian traffic. The Frontage Roads in Vail have also returned to their normal two-way configuration with a lane of travel in each direction.
Project Facts
- Cost:
$30 million - Average Annual Daily Traffic:
29,000 (I-70) - Contractor(s): Kraemer North America LLC
Project Schedule
October 2015
- Construction begins on I-70 detour crossovers. This involves putting down temporary asphalt in the median between the eastbound and westbound lanes of I-70. This pavement will eventually be used to divert all I-70 traffic onto one side while work is done on the opposite side of the highway. Although the crossover detours will be built in October, they will not be used until full underpass construction begins in the spring of 2016. Doing this work in October helps mitigate potential weather-related delays.
Spring 2016
- Full construction of the underpass begins and the crossover detours are put to use.
July 2016
- Planned completion of new bridge.
- Frontage Road traffic will be detoured to accommodate construction of lower frontage road, subsequent underpass and roundabout.
Winter 2016/2017
- Suspension of crossover detours and Frontage Roads restored to normal/full capacity during the winter tourist season.
Spring & Summer 2017
- Frontage Road detours reestablished to allow for final roundabout construction, landscaping work and installation of aesthetic components.
Fall 2017
- Project completion
Project Background
Growth and tourism in and around Vail have increased congestion on the roads most traveled in the area (interchanges from I-70 and along the north and south I-70 frontage roads). The idea of an additional underpass between West Vail and Main Vail has been discussed since the 1980s as a way to enhance connectivity and reduce congestion at the West Vail and Main Vail interchanges.
The I-70 Vail Underpass project will add an I-70 underpass near I-70 mile point 175, connecting the north and south frontage roads between the Main Vail and West Vail interchanges.
Construction, which started in April 2016, is scheduled to be completed in November 2017. Work hours will vary based on the construction phase (see below). The tentative project schedule aims to reduce construction impacts during the winter tourism season.
The first major phase of construction involved moving I-70 traffic into a single lane, barrier-separated configuration on one side of the highway while the bridge on the opposite side was built. I-70 traffic was initially shifted to the south side of the highway (in the eastbound lanes) to build the westbound bridge.
Once the westbound bridge was completed, traffic was shifted to the north side of the highway (westbound lanes) while the eastbound bridge was built. Both of the underpass bridges were completed by July 1, 2016.
This phase consists of a winter slowdown of major construction to allow for a normal traffic alignment along the north and south frontage roads during the winter tourism season.
There is the potential for minor construction activities beneath the underpass, although no night or week work is anticipated.
Traffic Impact:
The frontage roads' normal two-way operation through the construction site will continue, allowing eastbound and westbound travel on both the north and south frontage roads. I-70 is in its normal two-lane, two-way traffic alignment.
The new underpass will be closed during phase 3 to both vehicle and pedestrian traffic.
Bikes and Pedestrians:
Access to the Gore Creek Trail on the east end of the project site (adjacent to the Glen Lyon offices) is open to pedestrians and bicyclists. Pedestrians on the south frontage road are advised to use the Gore Creek Trail.
The North Recreation Path, adjacent to the north frontage road, is open in its new at-grade alignment.
This phase focused on the construction of the underpass roundabouts. The area beneath the underpass was also fully built, including brick pavers, curb and gutters, and lighting elements. This phase also included construction of elevated sidewalks with pedestrian guardrails. Finer detail work—namely landscaping and aesthetic components were also completed.