I-25 Expansion, Colorado Springs to Monument
Project Overview
The Interstate 25 (I-25) Expansion Project was an 11-mile, design-build project in northern El Paso County that added one lane in each direction of I-25 between Woodmen Road in Colorado Springs and State Highway 105 in Monument. The capacity improvements to this stretch of the interstate were designed to improve mobility and safety.
A major transportation corridor for the state, I-25 connects more than three million residents along the Front Range from Denver, Colorado Springs and Pueblo, to destinations in northern Colorado.
As the only north-south freeway within El Paso County, it is the region’s most heavily traveled roadway, serving more than a half million Pikes Peak area residents. Population growth, and projected continued growth, has resulted in increased corridor congestion.
In alignment with the South Front Range Corridor Assessment’s recommendation to address congestion within urban areas, the I-25 Expansion: Colorado Springs to Monument project was identified as a priority to alleviate congestion and improve safety for the traveling public.
During peak travel hours, this segment of I-25 experienced significant traffic backups. The expansion project benefited local residents and businesses, improved the trip for those driving this segment of the interstate and contributed to regional economic vitality by making it easier to reach Colorado Springs.
The project improved mobility and safety by:
- Widening 11 miles of I-25 (northbound and southbound) from 2 lanes to 3 lanes, Woodmen Road to Monument exit
- Adding auxiliary lanes at on/off ramps between Woodmen Road and Interquest Parkway
- Changing the ramp configuration at North Gate Boulevard
- Relocating and improving the Ackerman Overlook
- Relocating and expanding the truck chain-up station currently located south of Baptist Road
The Colorado Department of Transportation (CDOT) contracted with Kiewit Infrastructure Co. (Kiewit), in association with its design sub-consultant Parsons Brinckerhoff (PB), to design and construct the I-25 Expansion project. The Kiewit/PB design-build team was committed to delivering a quality project that met CDOT’s four goals for expanding I-25 capacity.
- Alleviate corridor congestion
- Minimize impacts to the natural environment
- Reduce project impacts to travelers
- Complete the project by Dec. 31, 2014 (CDOT mandatory completion date)
The project protects habitat and wetlands, improves access onto and off the interstate, eases congestion along this stretch of I-25, and improves safety to the traveling public.
What is Design Build?
Under the design-build process, the same contractor is responsible for the project’s design and construction. CDOT provides a general concept of the plan, and the contractor is responsible for most of the details, many of which are worked out as the project proceeds.
Employing design-build, construction begins before the project design is complete. This results in projects being completed more quickly than projects constructed using the more common design-bid-build process.
Using the design-build process, CDOT establishes project scope, goals and design criteria and selects a team based on “best value,” which often enables CDOT to expand the scope of work and stretch limited project funding.
Project Facts
- I-25 through Colorado Springs was built between 1955 and 1960 and was originally called the Monument Valley Freeway.
- Funding for the I-25 Expansion project is $66.4 million
- Colorado Department of Transportation: $50.4 million
- Pikes Peak Area Council of Governments: $8 million
- Federal Highway Administration: $8 million
- At its peak, 200 people will be working on the expansion project.
- The contractor will pay approximately $30 million to local businesses for labor, materials and equipment; a direct local economic impact.
- 75 pieces of heavy equipment will be used at any given time.
- Currently, 100,000 vehicles per day travel north of Woodmen Road on I-25. This number is projected to increase to 145,000 vehicles at Woodmen Road by 2025.
- Four bridges will be expanded in the I-25 Expansion construction zone.
- The bridges over North Gate Boulevard are already wide enough to accommodate a third lane in each direction.
- To expand the bridges, 24 new bridge girders will be placed.
- 250,000 tons of asphalt will be laid as part of the project. This is equivalent to paving a 5-foot wide, 4-inch deep sidewalk stretching 375 miles from Colorado Springs to Albuquerque, N.M.
- While the project corridor is about 11 miles long in one direction; there are 75 total lane miles.
Project Schedule
Milling and paving will extend to daytime hours beginning Aug. 8
- Temporary lane shifts to allow three lanes of through traffic along most of northbound and southbound I-25
- The segment of I-25 near North Gate Boulevard is wide enough to only accommodate two through lanes while milling and paving is completed. Our goal is to evaluate milling and paving options in this area to minimize travel impacts.
- Daytime speed limits will be reduced to 55 mph where milling and paving are taking place
- Nighttime speed limits will remain at 45 mph where milling and paving are taking place
Subject to weather and road conditions, daytime milling and paving will take place Monday through Saturday while maintaining two through traffic lanes.
Nighttime work will continue six nights a week, Sunday through Friday. Friday night lane and ramp closures will begin at 9:30 p.m. and will be open by 7:30 a.m. the next morning.
Drivers can expect to see heavy truck traffic in the area as asphalt is delivered for the paving work.
Final paving is scheduled end in late summer.
- Construction begins – March 1, 2013
- Capacity improvements (additional lane each direction) complete – Dec. 31, 2013
- Final milling and additional asphalt complete – summer 2014
- Project complete – Dec. 31, 2014
Phase 1: Widening Segments 1 and 3
- Segment 1: Woodmen Road to N. Academy Boulevard – Barrier will be placed to the outside lanes (right of existing traffic lanes) to make a work area to the outside where widening will occur. This work includes reducing the number of northbound lanes from 3 to 2 between Woodmen Road and N. Academy Boulevard. Work scheduled: April to May 2013.
- Segment 3: Briargate Parkway to north of Black Squirrel Creek – Barrier will be placed in the right shoulder to designate the work area to the outside of the existing lanes. Traffic will shift toward the highway median. Work scheduled: March to May 2013.
Phase 2: Widening Segments 2, 4 and 5
- Segment 2: N. Academy Boulevard to Interquest Parkway – Barrier will be place along the left shoulder of the highway to make a work area to the inside where widening will occur. Travel lanes will shift to the outside with a reduced left and right shoulder. Work scheduled: June to August 2013.
- Segment 4: Split section (wide median) of I-25, south of Black Squirrel Creek to just north of North Gate Boulevard – Barrier will be placed in the shoulder of the left lane to make a work area in the median where widening will occur. Work scheduled: June to August 2013.
Phase 3: Segment 5
- Reconfigure the I-25/North Gate Boulevard interchange to a diamond style. Work anticipated in July 2013.
- North of North Gate Boulevard to State Highway 105 – Barrier will be placed in the right shoulder to designate the work area to the outside of the existing lanes. Work scheduled: August to October 2013
Phase 4: Mill and Overlay All Lanes
- Majority of work performed at night
- Mill and overlay all existing lanes and shoulders between Woodmen Road and Monument
- Final pavement marking and signage
- Final landscaping
Drainage Work
- Traffic remains in current configuration
- Install temporary stormwater control features, such as silt fence, erosion logs and berms
- Extend existing concrete box and pipe culverts
- Install additional drainage culverts
- Replace Black Squirrel Creek bridges and widen bridge culvert at Jackson Creek
Frequently Asked Questions
| faqs |
|---|
| Project Background |
| Project Construction |
| Northgate Interchange |
| Environmental |
Project background
Q: What is the @i25expansion project?
A: The @i25expansion project will add one traffic lane in each direction on the corridor (from 2 to 3 lanes in each direction) in addition to building auxiliary lanes between Woodmen Road and Interquest Parkway.
Q: Why is this project necessary?
A: The capacity improvements to this stretch of the Interstate 25 (I-25) are designed to improve mobility and safety between Woodmen Road in north Colorado Springs and State Highway 105 in Monument. Steady growth, while beneficial to the region’s livelihood, is overwhelming this section of I-25 and frustrates drivers during peak travel periods. Incidents on the corridor, in addition to traffic volumes during peak travel periods, add to the daily challenges of driving this 11-mile section of I-25.
Q: What are auxiliary lanes?
A: Auxiliary lanes include those lanes other than the main driving lanes of a roadway, such as turn lanes or truck lanes, merge lanes and passing lanes. Auxiliary lanes currently exist on northbound I-25 between Woodmen Road and N. Academy Boulevard and between N. Academy Boulevard and Briargate Parkway. Vehicles entering northbound I-25 at N. Academy Boulevard have the option of merging with northbound traffic or staying in the auxiliary lane to exit at Briargate Parkway. The existing auxiliary lanes will be maintained while a new auxiliary lane will be added between Briargate Parkway and InterQuest Parkway through this expansion project.
Q: What are the Colorado Department of Transportation (CDOT) goals for this project?
A: The project goals are:
- Alleviate corridor congestion
- Minimize impacts to the natural environment
- Reduce project impacts to travelers
- Complete the project by Dec. 31, 2014 (CDOT mandatory completion date)
Q: What is the contractor’s proposed construction schedule?
A: The contractor’s schedule is:
- Construction begins March 1, 2013
- Capacity improvements (an additional lane in each direction) completed by Dec. 31, 2013
- Final milling and asphalt overlay of existing lanes completed by summer 2014
Q: What is the project budget?
A: The budget for the @i25expansion project is $66.4 million. Funding comes from the following agencies:
- Colorado Department of Transportation: $50.4 million
- Pikes Peak Area Council of Governments: $8 million
- Federal Highway Administration: $8 million
Q: What does Design-Build mean?
A: Under the design-build process, the same contractor is responsible for the project’s design and construction. CDOT provides a general concept of the plan, and the contractor is responsible for most of the details, many of which are worked out as the project proceeds. Employing design-build, construction begins before the project design is complete. Frequently this results in projects being completed more quickly than projects constructed using the more common design-bid-build process. Using the design-build process, CDOT establishes project scope, goals and design criteria and selects a team based on “best value,” which often enables CDOT to expand the scope of work and stretch limited project funding. Both the T-REX interstate/light rail expansion project in Denver and the COSMIX interstate expansion project in Colorado Springs were design-build projects. T-REX, a project of CDOT and Denver’s Regional Transportation District, was completed more than a year ahead of schedule. COSMIX, a CDOT project, was completed more than a year ahead of schedule.
Q: Did this project require the purchase of any additional right-of-way?
A: No additional right-of-way was needed for this expansion project; however, several temporary easements were required to accomplish drainage and other work off of the highway.
Q: How many local many local jobs will be created to support this project?
A: The number of jobs created locally is difficult to pinpoint; however, at its peak, 200 people will be working on the project. While the contractor will use some of its project management staff from outside the local area, local employees of the contractor as well as additional hires will work on the project.. And, the contractor is expecting to spend $30 million locally for labor, materials and equipment; a direct economic impact.
Q: Will the @i25expansion project include work for the Powers Boulevard interchange with I-25?
A: No, this project will not include work for the Powers Boulevard/I-25 interchange.
Q: How many vehicles pass through this corridor each day?
A: Currently, 100,000 vehicles per day travel north of Woodmen Road on I-25. This number is projected to increase to 145,000 by 2025.
Q: How can I get construction information to plan my travels?
A: To register for email and/or text message project updates, visit www.coloradodot.info and click on the green cellphone in the upper right corner of the website.
Project Construction
Q: What is the paving schedule for the project?
A: Milling and paving work will take place both during the day and at night. Daytime paving is being added to expedite construction and makeup for work lost to weather delays. Daytime milling and paving will result in:
- Temporary lane shifts to allow three lanes of through traffic along most of northbound and southbound I-25
- The segment of I-25 near North Gate Boulevard is wide enough to only accommodate two through lanes while milling and paving is completed. Our goal is to evaluate milling and paving options in this area to minimize travel impacts.
- Daytime speed limits will be reduced to 55 mph where milling and paving are taking place
- Nighttime speed limits will remain at 45 mph where milling and paving are taking place
Subject to weather and road conditions, daytime milling and paving will take place Monday through Saturday while maintaining two through traffic lanes.
Nighttime work will continue six nights a week, Sunday through Friday. Friday night lane and ramp closures will begin at 9:30 p.m. and will be open by 7:30 a.m. the next morning.
Drivers can expect to see heavy truck traffic in the area as asphalt is delivered for the paving work.
Final paving is scheduled end in late summer.
Q: Where will the additional lanes be built?
A: Based on available space and land configurations, the new lanes generally will be added to the outside of the existing interstate lanes. In some sections where the medians are wide, the lanes will be added between the northbound and southbound lanes.
Q: Will speeds be reduced for the entire length of the project during construction?
A: Yes, speeds will be reduced for the entire 11-mile length of the project corridor for the protection of drivers and work crews. During construction, driver and worker safety is our #1 priority. To help reduce the chance of mishaps, speeds in the construction zone will be reduced to 55 mph in areas where the posted speed is currently 65 mph. In areas where the posted speed is 75 mph, speeds will be reduced to 65 mph. When night work takes place and traffic is reduced to one lane, speeds will be reduced to 45 mph.
Q: Will there be lane closures during construction?
A: The four existing lanes of I-25 will not be closed during peak travel times, which are from 5:30 a.m. to 8:30 p.m., Sunday through Thursday. Temporary lane reductions and closures, when necessary, will take place between 8:30 p.m. and 5:30 a.m., Sunday through Thursday.
Q: Will the backup warning signals on equipment be muffled?
A: While we don’t anticipate noise issues with warning signals on equipment, we will address concerns should they arise. It’s important to remember that backup warning signals are to help ensure worker and equipment safety.
Q: How much asphalt will be used on I-25?
A: The project will use 250,000 tons of asphalt on the additional lanes and to repave the existing traffic lanes. This is equivalent to paving a 5-foot wide, 4-inch deep sidewalk stretching from Colorado Springs to Albuquerque, N.M.
Q: What will happen to the asphalt milled from the existing lanes of I-25?
A: The milled asphalt will be recycled and used in the asphalt mix used to repave the existing lanes.
Q: Will there be an asphalt batch plant on site?
A: There will not be an asphalt batch plant in the project corridor. Asphalt to pave the new lanes and to repave the existing lanes will come from Kiewit’s asphalt plants in Colorado Springs and Sedalia, Colorado, near Castle Rock.
Q: Will the new lanes be opened as they are completed or will they open once all construction is complete?
A: The additional traffic lanes (one in each direction) will open once construction on those lanes is complete, which is expected by Dec. 31, 2013.
Q: How will construction be handled during special events at the Air Force Academy, such as graduation and home football games?
A: The contractor team is working closely with the Air Force Academy to ensure construction does not interfere with events that draw heavy traffic to the Academy. That coordination extends to other special events and organizations in the local area and the Pikes Peak region.
Q: How will stranded motorists be handled in the construction corridor?
A: A courtesy patrol will be available to help motorists who may become stranded in the corridor during construction. The patrol will operate between 7-9 a.m., and 3-6 p.m., Monday-Friday and during some special events. Courtesy patrol staff will help passenger and other smaller vehicles by providing free roadside assistance such as flat tires, fuel or water transfer, jump starts, short-distance towing, accident scene protection and minor mechanical help.
Q: When will the Ackerman Overlook reopen?
A: The overlook, which will close in late March, will move north of its current location and will be improved and expanded. The popular and historic overlook will remain closed until construction is complete on the additional traffic lane, which is expected by Dec. 31, 2013.
Q: When will the truck chain-up station reopen?
A: The chain-up station, currently located on the east side of the interstate, south of Baptist Road will close in mid March and be relocated on the same side of the interstate north of the Baptist Road interchange, close to the Monument Marketplace retail center. The chain-up station will be expanded and improved to accommodate more trucks in a safe environment.
Q: What is the purpose of the trailer at the southwest corner of I-25 and Baptist Road?
A: The trailer serves as the project construction and materials testing office.
North Gate Interchange
Q: How will the North Gate Boulevard interchange be improved?
A: The interchange will be improved by modifying the ramps where they intersect North Gate Boulevard to accommodate traffic signals or by adding roundabouts to improve traffic flow, safety and to enhance the interchange, which serves as the primary visitor entry point to the U.S. Air Force Academy.
Q: What will the improvements be to North Gate Boulevard at Struthers Road?
A: Currently, there are no improvements planned for this intersection as part of the @i25expansion project.
Q: Will the new North Gate Boulevard interchange be designed to accommodate the future Powers Boulevard connection to I-25?
A: Yes, the North Gate Boulevard/I-25 interchange design will accommodate the future Powers Boulevard interchange, which will be just south of the existing North Gate Boulevard interchange.
Environment
Q: How will stormwater issues be mitigated?
A: The Kiewit/Parsons Brinckerhoff team is working closely with local, state and federal agencies, including the Air Force Academy, to address stormwater issues that exist along the project corridor. Early construction activities include installing temporary stormwater control features, such as silt fence, erosion logs and berms. Work includes extending existing concrete box and pipe culverts and installing additional drainage culverts to address existing, and potentially future, drainage issues.
Q: How will the contractor minimize impacts to the natural environment?
A: The contractor team is minimizing environmental impacts by:
- Focusing on water quality Best Management Practices both during and after construction.
- Protecting the Preble’s Meadow Jumping Mouse habitat by avoiding construction during the hibernation season.
- Protecting wetlands and reducing stream and habitat impacts by extending and improving existing drainage systems rather than replacing them.
- Locating construction staging areas way from adjacent streams and wetlands areas.
- Controlling dust during construction, which includes wetting disturbed areas.