US 36, Pearl Street to 55th Street - Wetland Mitigation

About the Project

Creation of new wetland area to mitigate wetland loss due to US36 Express Lanes project. Approximate cost for this project is $4 million, and slated to begin in June 2015 and scheduled for completion in June 2016. 

Traffic Impacts

Minimal impacts to traffic as work is off the road.