US 50, US 550 & US 160 Chain Station Safety Upgrades

Project Complete

Project Facts

  • Cost: $1.4 million
  • Contractor: Interface Communications Company
  • Timeline: August 2018 - June 2019
  • Location: At eight chain-up/chain-down locations off US Highways 50, 550 and 160 in Chaffee, Mineral, Ouray, Saguache and San Juan counties

About the Project

In August 2018, crews began upgrading eight trucking chain-up/chain-down stations at five locations across Southwest Colorado. Specifically, crews will:

  • install lights and pull boxes;
  • pave graveled areas with asphalt; and
  • place a new electronic message board at a station in Ouray.

Work will enhance safety for truckers using these stations.

The five work locations are:

  1. US 50, Monarch Pass East/West, at mile point (MP) 190.1 in Saguache County;
  2. US 50, Monarch Pass East/West, at MP 201.9 in Chaffee County;
  3. US 160, Wolf Creek Pass, at MP 176.6 in Mineral County;
  4. US 550 Silverton and Ouray at MP 70 in San Juan County; and
  5. US 550 Silverton and Ouray at MP 95 in Ouray County.

Schedule

  • Work hours: 7 a.m. - 7 p.m., Monday - Friday