Description of Work Resurfaces 14 miles of I-70 from milepost 190 to 204 as well as the right lane of eastbound I-70 between milepost 180 and 190. Numerous bridges along the I-70 corridor will also be rehabilitated by repairing expansion joints and bridge decks.
Project Owner CDOT
CDOT Region 1
County Eagle and Summit
Estimated Total Project Cost $10,068,510
ARRA Funds $8,000,000
Project Status Completed
Start Date June 1, 2009
Completion Date Summer 2010
Percentage Spent N/A
Contractor Asphalt Paving Co.
 