CO 74 Rockfall Mitigation Project

About the Project

The Colorado Department of Transportation and contractor Midwest Rockfall, Inc. will begin a rockfall mitigation project in Bear Creek Canyon, which is along Colorado Highway 74 between Morrison and Idledale. Work will involve week day full closures on CO 74 between Morrison and Idledale from Mile Point 16.1 to MP 18. Please see the detour map below. 

The project will enhance safety for motorists and cyclists along CO 74 with a goal of preventing roadway damage or unexpected closures caused by a natural rockslide.

What work will be done?
Crews will conduct rock scaling operations, install anchored wire mesh and other rock reinforcement, and use Polyurethane Resin (PUR) injections which is an innovative technology applied to fill the void between loose rocks.

Due to the nature of rockfall mitigation, full closures must occur for the safety of the traveling public. This part of CO 74 is a narrow canyon with limited areas for crews to maneuver equipment and the rock scaling operations may result in some rockfall on the roadway, which is why full closures are necessary during work hours.

Project Facts

  • Cost: $2.9 Million
  • Contractor: Midwest Rockfall Inc.
  • Timeline: September - February 2021
  • Location: CO 74 between Morrison and Idledale (Bear Creek Canyon)

View the Project Fact Sheet



Proposed Work Schedule

  • Work is scheduled to begin Sept. 2 and continue through Feb. 2021. However, these operations are weather and temperature dependent, and this schedule could change.
  • The full closures will begin Tuesday, Sept. 8 and occur during working hours, Mondays through Thursdays from 4:30 a.m. to 4:30 p.m., and on Fridays from 4:30 a.m. to 12:30 p.m. No weekend work or closures are anticipated.

Traffic Impacts

  • On Wednesday, Sept. 2 and Thursday, Sept. 3, crews will place traffic in a single-lane configuration on CO 74 with flaggers on site from 7 a.m. to 5 p.m.  Motorists can expect delays of up to 20 minutes.
  • Starting Tuesday, Sept. 8, there will be full closures of CO 74 between Morrison and Idedale (MP 16.1 -18) in place during working hours.
  • Typical working hours will be 4:30 a.m. to 4:30 p.m. Mondays through Thursdays, and 4:30 a.m. to 12:30 p.m. on Fridays. No weekend work or closures are anticipated.
  • This schedule will remain in effect through Feb. 2021. (weather permitting)
  • Motorists are advised to follow the detour signs and seek alternate routes.
    • Interstate 70 is the general detour route for east and westbound motorists.
    • Local traffic on CO 74 can take Parmalee Gulch Rd southbound from Kittredge and use US 285 to connect with C-470, or head northbound via S Grapevine Road from Idledale to connect with I-70.
    • These county roads (Parmalee Gulch and S Grapevine) are for local traffic only. Trucks or large vehicles should detour via I-70.
  • Cyclists are prohibited from riding through the construction zone during the working hours listed above.
  • Fishing in the creek below the work site will be “fish at your own risk”

Detour Map

Detour map for CO 74 Rockfall Mitigation project