CO 142 ADA Ramp Improvements in Manassa

Work this Week

Oct. 24, 2021

Ongoing Traffic Impacts

The Region 5 ADA Ramp Improvements Project - Manassa will be conducted along CO 142 (Main St.) 9th St., 8th St., Mid-Block between 8th St. and 7th St., 7th St., 6th St., 4th St., 3rd St., 2nd St., and Mid-Block between 1st St. and 2nd St.

Monday, Oct. 25 to Friday, Oct. 29 work will consist of:

  • Eastbound and westbound right shoulder closure on CO 142 (Main St.) from 4th St. to 8th St.
  • All intersections and businesses will maintain public access
  • If the orange traffic barrels are pushed up against the curb you MAY park your vehicle in that area
  • If the orange traffic barrels are pulled out to the white line please do NOT park your vehicle in that area
  • The project will be in operation Monday through Friday from 8 a.m. to 5 p.m.
  • For more information or tobe added to the project update list please call 719.938.0388 email [email protected]

About the Project:

The Colorado Department of Transportation and Contractor KSK, LLC will Construct ADA ramp and sidewalk improvements in the community of Manassa Conejos County. Work will take place along CO 142 (Main Street) at various locations from MP 1.75 to MP 3.80.

Intersection improvements along CO 142:

  • 9th Street
  • 8th Street
  • Mid-block between 8th Street and 7th Street
  • 7th Street
  • 6th Street
  • 4th Street
  • 3rd Street
  • 2nd Street
  • Mid-block between 1st Street and 2nd Street

Work Schedule

  • Work is scheduled to begin Aug. 9 and is expected to last until late September. Normal working hours will be Monday through Friday from 7 a.m. to 7 p.m.

Traffic Impacts

  • Travelers by car, bike, wheelchair or foot can expect various lane and sidewalk closures where work zones exist.
  • Sidewalks may be closed overnight or over weekends to allow the concrete to set.
  • Access to all businesses will be maintained but may be temporarily altered.

Project Facts

  • Cost: $0-$1 Million
  • Contractor: KSK, LLC
  • Timeline: August - September 2021
  • Location: Various locations along CO 142 in Manassa

Manassa Main Street Project Map

Click image to enlarge