CO 392 & CR 55 Turn Improvements

Project Complete!

The CO 392 & CR 55 turn improvements project in Weld County have been completed.

The Colorado Department of Transportation has concluded construction on the CO 392 and CR 55 turn improvements project in Weld County earlier this month. This project, located on the southwest turn corner of CO 392 and CR 55 at Mile Point 123.5, began in early August. Mountain Constructors was selected for this project.

Crews worked on widening on the southwest turn corner of CO 392 and CR 55. Additionally they worked on the creation of a channelizing island on the southeast corner along with stop sign relocation, signing, and delineator installation.

Project Facts

  • Cost: $ 174,037
  • Contractor:  $174,037
  • Timeline: July - September 2022
  • Location:  On the southwest turn corner of SH392 and CR55 at MP 123.5.

CO 392 & CR 55 Project Map