CO 74 Resurfacing in Evergreen

About the Project

The project will consist primarily of roadway resurfacing which will include a mill and overlay.

Additional operations will include:

  • Utility upgrades
  • Shoulder widening
  • Guardrail removal and replacement
  • Concrete curb ramp upgrades to meet Americans with Disabilities Act standards
  • Bridge rehabilitation work over Bear Creek.

Work this Week & Lane Closures for CO 74 Bear Creek Road Resurfacing

Project Facts

  • Construction Cost: $6.5 million
  • Contractor: Brannan Sand and Gravel
  • Timeline: May 2026 to October 2026
  • Location: CO 74
    • Nearest Town/City: Evergreen
    • Mile Point(s): MP 6.9 to MP 12.5
    • County: Jefferson
Map of project work zone on CO 74 between Evergreen Lake and Lair O' the Bear Park
Map of project work zone on CO 74 between Evergreen Lake and Lair O' the Bear Park

Project Benefits

  • Resurfacing efforts will provide a smoother driving experience. Studies show an even roadway surface decreases everyday wear-and-tear on vehicles and allows for better driver control in variable weather conditions.
  • Upgraded curb ramps will enhance pedestrian accessibility for those who walk, roll and stroll through the corridor.
  • Guardrail replacements will offer added safety benefits to motorists traveling along the winding mountain highway.

Work Schedule

  • Construction will start in May and continue through Fall 2026
  • General working hours are Monday through Friday from 7 a.m. to 5 p.m.
  • Milling and paving operations on the west end of the project zone through the town of Evergreen will occur overnight from Sunday night through Friday morning, 8 p.m. to 7 a.m.
  • All other operations are anticipated to take place during daytime hours

Traffic Impacts

  • Motorists can expect daily traffic shifts and single-lane closures with one through-lane maintained most days
  • Sections of the highway will be reduced to a single lane with flagging operations periodically throughout the project
  • Business and residential access will be maintained during daytime hours with temporary restrictions during milling and paving operations
    • All affected properties will be notified prior to any access interruptions.
  • Sidewalk access will be restricted intermittently through downtown Evergreen with pedestrian detour routes in place
  • The highway will narrow to 12 feet at several locations
  • Various speed reductions will be in place for the duration of the project
  • While significant delays are not expected, motorists are encouraged to account for up to 10 minutes of extra travel time when driving the corridor
  • Drivers should use extra caution around cyclists on lane-restricted roadways, particularly during summer months when cyclist traffic increases
  • Refer to COtrip.org for real-time travel conditions and road closures