I-25 Cable Barrier between Pueblo and Colorado Springs

Project Facts

  • Cost: $3.5 million
  • Contractor: Kirkland Construction
  • Timeline: June - December 2019
  • Location:  along I-25 between the Pikes Peak International Raceway and the city of Fountain, from mile points (MP) 122 to 128

Crews are installing and resetting median cable barrier along I-25 between Pueblo and Colorado Springs to prevent median crossover crashes.

This work is in response to the substantial crash history and increased traffic volumes in this area. Crews will:

  • Install and reset median cable barrier on new geometric alignment to address median crossover crashes.
  • Regrade earthwork approaches.
  • Patch with hot-mix asphalt.
  • Improve drainage.
  • Complete erosion control measures.
  • Provide space for patrol and emergency vehicles to pull over.
  • Create flatter slopes to reduce maintenance costs.
  • Reduce the number of hits to the cable, reducing maintenance needs.

Schedule

  • Most work will occur overnight Sunday through Thursday, with some weekend and daytime work possible.
  • All work is weather dependent and subject to change. 
Contact Us


 