I-70 Bridge Over Washington Street

Project Complete!

The Colorado Department of Transportation and ABCO Contracting began work to improve the I-70 bridge over Washington Street in Denver County in May. The project includes bridge deck repairs, storm sewer removal and replacement, bridge expansion device replacements, and median wall replacements. The project zone will span the length of the I-70 bridge (Mile Point 274.5 to MP 274.61) and will impact both east and westbound lanes.


Project Benefits

  • Critical repair work will provide greater safety for the traveling public.
  • Replacing bridge expansion devices will increase the overall longevity of the bridge's service life.
  • The project's bridge improvements will create smoother travel paths for motorists.

Work Schedule:

  • The project started the first week of May and is anticipated to be completed in December, 2023.
  • During the month of May, crews worked working daytime hours from 7 a.m. to 5 p.m., Monday through Friday.
  • After May, work transitioned to nighttime hours from 10 p.m. to 5 a.m., Sunday night through Friday morning. Night work is expected to continue through the end of the project.

Traffic Impacts:

Motorists can expect the following impacts during the period of construction:

  • From June through the fall of 2023, there will be nighttime single and double lane closures on I-70. This will include the Express Lane and general purpose lanes over Washington Street.
  • I-70 ramps to Washington Street will close intermittently during the night work with temporary detour routes in place. The ramps from I-70 to I-25 may experience single lane closures as well.
  • Crews will be replacing expansion joints and large steel plates will be placed on the roadway to help facilitate work.
  • Drivers are encouraged to exercise extreme caution traveling over the steel plates. Please slow down within the work zone, watch for construction vehicles entering the highway, and leave plenty of space between vehicles.
  • Traffic impacts are expected to be minimal with delays up to ten minutes.
  • Refer to COtrip.org for real-time travel conditions and lane closures.

Work this Week & Lane Closures
I-70 Bridge Over Washington Street

Project Facts

  • Construction Cost: $1.8 Million
  • Contractor: ABCO Contracting
  • Timeline: May - December 2023
    (The project was originally scheduled to be completed in October 2023, but the project is now expected to be completed in December. The delay is due additional median barrier work being added on to the project.)
  • Location: I-70 over Washington Street
    • Nearest Town/City: Denver
    • Mile Point(s): 274.50 - 274.61
    • County: Denver
I-70 over Washington Map of Project Work Zone
I-70 over Washington Map
of Project Work Zone