Projects

I-25, Ilex Street to City Center Drive

Project Progress

About 13 months into the I-25 Ilex Street to City Center Drive project in Pueblo, construction is progressing smoothly with minimal impact to travelers in the area.

Rehabilitation of Mesa Avenue over I-25 has begun, and crews are currently working on the roadway, bridge deck and substructure.

Foundation and substructure of I-25 over Indiana Avenue is underway, along with pile foundation work at Gruma Drive, and a Consolidated Mainline Bridge.

Installation of the D Street Mechanically Stabilized Earth Panel Walls continues.

The project is expected to be completed in 2018.


Schedule and Traffic Impacts

Normal working hours are from 7 a.m. - 7 p.m., Monday through Friday. There will be some nighttime and weekend work as needed.

Please use caution and stay alert while traveling through the construction zone.

TRAFFIC SHIFT ON SANTA FE AVENUE BEGINS JULY 5

  • Please be advised that beginning Wednesday, July 5 at 6 p.m., traffic will be reduced to a single lane in each direction on Santa Fe Avenue (US 50C) under Interstate-25 as northbound lanes are closed and traffic is shifted onto southbound lanes. Twelve-foot width restrictions will be in place.
  • The new traffic configuration will be in place 24 hours-a-day, 7 days-a-week through Sunday, July 16. Flaggers will be present during normal working hours of 7 a.m. to 7 p.m. Slight traffic delays are expected, speeds will be reduced to 25 MPH, and motorists are urged to use extra caution while traveling in the new traffic pattern.

In 2000, the Federal Highway Administration (FHWA) and CDOT initiated an Environmental Impact State Study (EIS) as part of the National Environmental Policy Act (NEPA) of I-25 through Pueblo, Colorado. This project was designed with respect for the traditions and trends of the Pueblo community, and is consistent with the New Pueblo Freeway EIS and aesthetic guidelines established for the I-25 corridor through Pueblo.

CDOT started this project in July 2015. The first segment of construction consists of replacing bridges on I-25 between Ilex Street and City Center Drive. Work includes rehabilitation of bridges on:

  • northbound I-25 over Santa Fe Avenue (US 50C);
  • I-25 over Indiana Avenue;
  • Santa Fe Avenue (US 50C) over the Arkansas River; and
  • Northern Avenue and Mesa Avenue over I-25.

The project was designed with respect for the traditions and trends of the Pueblo community. One section of the recently installed D Street wall panels displays the image of a baseball player, paying homage to Pueblo's beloved pastime.

The I-25/Ilex Design-Build project team is taking care to comply with environmental requirements and develop processes so work activities are protective of human health and the environment.

Funding

This project receives 60 percent Funding Advancements for Surface Transportation and Economic Recovery (FASTER) funds and 40 percent Responsible Acceleration of Maintenance and Partnership (RAMP) funds.

  • FASTER funding legislation pays for safety projects and repairs for structurally deficient bridges as well as safety improvements to Colorado’s key corridors.
  • RAMP program funds help move projects forward by funding multi-year projects based on year of expenditure, rather than saving for the full amount of a project before it starts.

Project Facts
 

  • Cost:
    $69 million

Project Team

  • Contractor(s): Flatiron Construction
Colorado: The Official State Web Portal