Region 3 ADA Ramp Improvements in Hayden

Work this Week

Week of August 9

Ongoing Traffic Impactshe Region 3 ADA Ramp Project will be conducted on US 40 (Jefferson Avenue) from 6th St. to Pine St.

The Monday, Aug. 10 to Friday, Aug. 14 work week will consist of:

  • Eastbound lane closure on Jefferson Ave. from 6th St. to Pine St.
  • Eastbound lane will be transitioned into center turning lane
  • All intersections will maintain public access
  • Expect intermittent flagging during construction
  • The project will be in operation Monday through Friday from 7 a.m. - 7 p.m.

Project Facts

  • Cost: $1 million
  • Contractor: KSK, LLC
  • Timeline: July 2020 - January 2021
  • Location: US 40 in Hayden, Routt County

About the Project

In July 2020 crews on this project will be working on providing improvements to curb ramps, curbs and gutters and sidewalks in the City of Hayden, Colorado.


Work Hours and Schedule

  • The project will be in operation Monday through Thursday 7 a.m. - 7 p.m. Drivers are asked to obey all construction road signs during this time.