Southeastern Colorado Bridge Bundle Project | Construction Phase

Region 2 Bridge Bundle Open House

Check out the Region 2 Bridge Bundle Open House to learn more about the project and expected impacts.

Open House

Work this Month
August, 2022

Traffic Impacts for the August include:

  • Colorado Highway 9 is OPEN to motor vehicles.
  • Beginning Wednesdy, Aug. 3 - Single lane closure with signalized, alternating traffic between MP 15.6 and 16.1. This traffic configuration will be in place for approximately three months.
  • General work hours are Monday through Friday from 7 a.m. to 6 p.m. with occasional extended hours and weekend work.
  • Expect delays.

About the Project:

CDOT, and its contractor partner CapitalTezak JV, will replace 17 rural structures across key highway corridors (CO 9, US 24 and US 350) in Region 2. The 17 rural structures that comprise the project area are on essential highway corridors in southeastern and central Colorado. The key corridors provide rural mobility, intra- and interstate commerce, movement of agricultural products and supplies, and access to tourist destinations. The $43 million project will start in summer 2022 and project completion is slated for winter 2024.


Project Facts

  • Cost:  A preliminary estimate of approximately $42.5 million for design and construction
  • Contractor: CapitalTezek
  • Timeline: June 2022 - December 2024
  • Location: Bridges on US 350, US 24 and CO 9