Projects

Weekly Construction Update

  • Concrete Pour for the Traffic Bridge Scheduled for 5 a.m. Saturday, Oct. 21
    Crews will pour concrete for traffic bridge at 5 a.m. Saturday. Anticipate noise and heavy machinery from 5 a.m. to 8 p.m. for the next several weeks—including weekends.
  • Sixth and Laurel Roundabout Work
    Crews are working to complete the Sixth and Laurel roundabout. Please follow flagger instructions and wayfinding signage if you are traveling through the area.
  • Crews continue to pour concrete barrier and parapets along the new traffic bridge.
  • Signal installation at the Sixth and Laurel roundabout is ongoing. Check out this week's Answer Man for more information on how the signals will work.
  • Crews are paving the Glenwood Hot Springs parking lot in the coming months.
  • Structural wall construction and caisson drilling continues on the north end of the project site.

Check out the Monday, Oct. 23 Answer Man column to see how your neighbors have worked together to plan ahead, team up and drive less during the GAB detour.