    Proposed Timeline Events Processed
    Issued: December 14, 2018  Request for Letters of Interest
    Deadline: January 31, 2019 Letters of Interest Due 
    Issued: March 15, 2019 Request for Qualifications (RFQ)
    Deadline: April 26, 2019 Statement of Qualifications Due (SOQ)

    Issued: June 10, 2019 

    Short List Selection of Design-Build Teams Announced
    Issued: June 10, 2019 Draft Request for Proposal (RFP)
    Issued: July 12, 2019 Final RFP 

    Issued: August 22, 2019

    RFP Addendum 1

    Deadline: October 30, 2019

    Proposals Due
    Announced: December 19, 2019

    Selection of Design-Build Team

    LAWRENCE CONSTRUCTION CO./RS&H, Inc.

    Winter 2019/Spring 2020

    Notice of Award

    Spring 2020

    Contract Procurement of Design-Build Team (Notice to Proceed)

    Spring/Summer 2020

    Construction Begins