Design-Build Process

  • UPDATE on Feb. 11, 2019: View the list of contractors who have submitted statements of interest: List of Contractors
  • UPDATE on Feb. 1, 2019: The CDOT Project Team hosted an informational meeting on Jan. 23, 2019 for contractors and teams intending to submit Letters of Interest. (Letters were due on Jan 31.) View the slide presentation, list of attendees and the questions and answers discussed at the meeting: Contractor Briefing – 01.23.19 
  • Design-Build Manual  This manual provides procedures, guidelines, information, and resources to successfully develop and implement a design-build contracting strategy that is unique, yet in compliance with Federal regulations, State Legislation and Department Policy.

PROPOSED DESIGN-BUILD SCHEDULE

The following documents will be added as they become available throughout the project:
Proposed Timeline Events Processed
Issued: December 14, 2018  Request for Letters of Interest
Deadline: January 31, 2019 Letters of Interest Due 
Winter/Spring 2019 Request for Qualifications (RFQ)
Spring 2019 Statement of Qualifications Due
Spring/Summer 2019 Short List Selection of Design-Build Teams Announced
Spring/Summer 2019 Draft Request for Proposal (RFP)
Summer 2019 Final Request for RFP 
Winter 2019 RFP Due
Winter/Spring 2020

Notice of Award

Spring 2020

Contract Procurement of Design-Build Team (Notice to Proceed)