Design-Build Process & Schedule

Update on December 19, 2019: 

LAWRENCE CONSTRUCTION COMPANY and RS&H, Inc. were selected as the team representing the Best Value and has been identified as the apparent successful bidder for contract award for the US 550/160 Connection South Design Build Project. Read: Final Selection Announcement

Learn about the Design-Build Process

Proposed Design-Build Schedule

SCHEDULE: The following documents will be added as they become available throughout the project:

Proposed Timeline Events Processed
Issued: December 14, 2018  Request for Letters of Interest
Deadline: January 31, 2019 Letters of Interest Due 
Issued: March 15, 2019 Request for Qualifications (RFQ)
Deadline: April 26, 2019 Statement of Qualifications Due (SOQ)

Issued: June 10, 2019 

Short List Selection of Design-Build Teams Announced
Issued: June 10, 2019 Draft Request for Proposal (RFP)
Issued: July 12, 2019 Final RFP 

Issued: August 22, 2019

RFP Addendum 1

Deadline: October 30, 2019

Proposals Due
Announced: December 19, 2019

Selection of Design-Build Team

LAWRENCE CONSTRUCTION CO./RS&H, Inc.

Winter 2019/Spring 2020

Notice of Award

Spring 2020

Contract Procurement of Design-Build Team (Notice to Proceed)

Spring/Summer 2020

Construction Begins

Previous D-B Process Activity