Denver Metro Traffic Signal Improvements

Project Facts

  • Cost:
    $400,000

Project Team

  • Contractor(s):
    Technology Constructors, Inc.

Project Overview

This project improved traffic signals at four locations throughout metro Denver in late 2016.

The most extensive work was performed at the northbound I-25 off-ramp intersection with Colorado Boulevard. The project added a third direct right turn lane from the northbound I-25 off-ramp to northbound Colorado Boulevard.

Crews also replaced a concrete median island, curb ramps, overhead lighting, signal heads and other signal equipment.

Traffic signal infrastructure to enable advanced vehicle detection was installed at three locations:

  • CO 83 and Bayou Gulch Road in Douglas County
  • US 85 and CO 67 in Douglas County
  • US 40 and Tower Road in the City of Aurora

Detection systems identify vehicles approaching a traffic signal. Data collected from loop detectors are then used for traffic management, which includes adjusting signal timing to meet demand.