C-1-0 Set DBE and OJT Contract Goals
The C-1-0 Set DBE and OJT Contract Goals flowchart and process guides listed on this page outlines the responsibilities of the CDOT Project Manager (Preconstruction), Region Civil Rights Office, and Civil Rights Business Resource Center within the DBE and OJT goal setting discipline for Construction Manager/General Contractor (CM/GC) construction contracts.
Flowchart C-1-0 Set DBE and OJT Contract Goals outlines the roles of the CDOT Project Manager (Preconstruction), Region Civil Rights Office, and Civil Rights Business Resource Center for setting DBE and OJT contract goals on a Construction Manager/General Contractor construction contract prior to final specification package. Information provided in this flowchart is outlined below.
Download C-1-0 Set DBE and OJT Contract Goals Flowchart
Flowchart C-1-0: Set DBE and OJT Contract Goals
- Start: Prior to final negotiations, when the project is at 90% Opinion of Probable Construction Cost, the CDOT Project Manager (Preconstruction) provides the necessary project information to obtain civil rights goals to the Region Civil Rights Office or Civil Rights Business Resource Center (depending on who manages the project) (Figure 1-1).
- Decision Item: Does the DBE and OJT program apply (based on the project’s funding type)?
• If yes, continue to step 3
• If no, notify the CDOT Project Manager (Preconstruction) that there are no DBE and OJT contract goals applied to the contract. - The Region Civil Rights Office or Civil Rights Business Resource Center sets the DBE and OJT contract goals (Figure 1-2 and 1-3).
- The Region Civil Rights Office or Civil Rights Business Resource Center provides the CDOT Project Manager (Preconstruction) with the Civil Rights Construction Goal Setting Form (if utilizing) or email the CDOT Project Manager (Preconstruction) with the assigned goals.
- The CDOT Project Manager continues to prepare documents for the project advertisement.
- Decision Item: Is there a change in the project (project scope, funding type, advertisement date etc.)?
• If yes, continue to step 7
• If no, the process ends. - The CDOT Project Manager (Preconstruction) notifies the Region Civil Rights Office or Civil Rights Business Resource Center of the changes to the project. The Region Civil Rights Office or Civil Rights Business Resource Center determines if the goals should be reevaluated.
- The process ends.
Process Guides
CDOT Project Manager (Preconstruction)
CDOT Region Civil Rights Office or Civil Rights Business Resource Center
- 1-2 DBE Goal Setting for Construction Manager/General Contractor - to be published
- 1-3 OJT Goal Setting